Skip to content

Deploy & RelocateServices

Hyperscale GPU rack integration and deployment.

Receiving, rack integration, cabling, verification and handoff delivered as one physical deployment program, across rows, halls and phases, for Vera Rubin NVL72, GB300 NVL72 and B300.

A row of racks holding large GPU chassis, each flanked by power cords dressed in uniform loops.
GPU rack row after integration and cabling.

Proof at scale

  • Mobilization in as little as 24 hours.

    For qualifying engagements, subject to location, project scope, staffing and site access.

  • 1,500+ Racks of hyperscale GB300 deployment experience.

  • Vera Rubin NVL72, GB300 NVL72 and B300: Crews ready for the latest NVIDIA platforms.

Service area
United States

01Scope

Physical GPU deployment scope.

For hyperscalers, AI infrastructure operators and GPU cloud providers bringing rack-scale capacity online, and for the developers and integrators delivering it. See tenant-side colocation installation for provider access and change-window requirements.

  • S-01

    Receiving and staging

    Racks and equipment received, inspected and reconciled at the dock, then staged by row and delivery wave.
  • S-02

    Rack integration and positioning

    Racks integrated and set in position to the approved layout, with rack movement agreed with the responsible party.
  • S-03

    High-density cabling

    Back-end, front-end and out-of-band fabrics cabled to the approved schedule: trunks, breakouts, dressing and labels.
  • S-04

    Physical verification

    Placement, labels, port maps and agreed physical-layer tests closed rack by rack.
  • S-05

    Phased delivery

    Programs planned by hall, row and delivery wave, with crews allocated to equipment arrivals and site readiness.
  • S-06

    Documentation and handoff

    As-installed records handed to the platform team at the close of each wave.

Liquid-side cooling work, facility electrical and mechanical construction and cluster software commissioning stay with the cooling contractor, the facility owner and the platform team.

02Method

Rack installation, verification and handoff.

Six stages, each with a named output. Coordination with OEMs, facility operators and other trades is planned from the first stage.

  1. 01

    Project scope and site requirements

    Work package, quantities, drawings, site rules and acceptance criteria reviewed and agreed.

    Output

    Scope definition

  2. 02

    Technical planning and resource allocation

    Methods, sequence, tools and test equipment planned; crew size and shifts allocated to the schedule.

    Output

    Execution plan

  3. 03

    Mobilization and site coordination

    Access, inductions and logistics arranged with the facility operator, the OEM and other trades.

    Output

    Mobilization plan

  4. 04

    Physical installation and cabling

    Racks, equipment, fiber and copper installed to the approved layout and cable schedule.

    Output

    Installed racks

  5. 05

    Inspection, agreed testing and remediation

    Work inspected, agreed tests run, defects logged, remediated and rechecked.

    Output

    Closed defects

  6. 06

    Documentation and handoff

    Rack, cabling and test records assembled and handed to the owner of the next stage.

    Output

    Handoff package

A long row of open-rear server racks with vertical power distribution units and power cords dressed in repeating loops.
Rack row after installation and cable dressing.

Rapid response

Proposal Friday. Crew on site Monday.

03Platforms

Ready for Vera Rubin NVL72.

The latest NVIDIA platforms. Product names identify the equipment; the scope follows each OEM configuration.

  • Next generation

    Vera Rubin NVL72

    Deployment programs for Vera Rubin NVL72, planned to the OEM configuration and the site's delivery waves.
  • Blackwell Ultra

    GB300 NVL72

    Rack integration, high-density cabling and verification, backed by 1,500+ racks of hyperscale GB300 deployment experience.
  • Blackwell Ultra

    B300

    HGX B300 and DGX B300 systems racked, cabled and verified to the exact OEM configuration.

04Questions

Complete deployment FAQ.

Is this a full turnkey data center or GPU-cluster service?

It is the complete physical deployment of the racks: receiving, integration, cabling, verification and handoff, delivered as one program.

Can one physical deployment scope begin after receiving or rack assembly is already finished?

Yes. The program starts at whichever stage your project has reached.

Can you guarantee the deployment date or a production-ready cluster?

We commit to a schedule once site readiness, equipment arrivals and access are confirmed, and staff the crews to it.

Who supplies equipment and materials?

You or your appointed suppliers. We reconcile every delivery against the build list and flag gaps before installation.

Can rack work proceed while a cabling input is unresolved?

Yes, where the rack work does not depend on it. Dependent cabling waits for the released input, so nothing is installed twice.

How should we plan the people needed for parallel workfronts?

By workfront. Each hall, row or delivery wave gets its own crew plan, sized to equipment arrivals and site readiness.

Contact

Planning a hyperscale deployment?

Share your project scope, deployment schedule and infrastructure requirements. We will review the work package and discuss execution options.