LEVIATHAN SYSTEMS

GPU Cluster Deployment Estimator_

Enter a GPU count and planning example to explore illustrative rack and power arithmetic, with cooling interfaces to confirm—from H100/H200 HGX through GB200 and GB300 NVL72. No deployment schedule is calculated.

Rack groups (assumed)
114
72 GPUs per rack assumed
IT power subtotal (assumed)
13.7 MW
120 kW per rack assumed
Facility allowance (illustrative)
~17.8 MW
IT subtotal × assumed factor 1.3
Cooling planning category
Liquid path assumed
DGX guide: CPU/GPU cold plates plus other air-cooled loads
Scale-out positions (assumed)
~8,192
1 assumed position per entered GPU
Schedule
Not estimated
Needs work scope, site releases and an agreed calendar

Illustrative arithmetic only. Rack density and kW per rack are the displayed scenario assumptions; the facility allowance multiplies the IT subtotal by 1.3. Scale-out positions assume one per entered GPU, not a complete fabric or cable BOM. These outputs establish no OEM maximum, measured draw, available capacity or schedule. Confirm the exact equipment, remaining air and liquid interfaces, site releases and separately appointed acceptance owners before defining physical work.

Want a real scope for this build?
Discuss rack-and-stack, structured cabling and agreed physical verification. Liquid-cooling work and system commissioning are outside our service scope.
Talk to us

How this is calculated_

Rack groups divide the entered GPU count by the selected assumed GPUs per rack, round up and retain a minimum of one. The IT subtotal uses those groups times the displayed assumed kW per rack; the illustrative facility allowance multiplies that subtotal by 1.3. Scale-out positions equal the entered GPU count under a one-position-per-GPU assumption, not a complete populated fabric or cable BOM. These calculations do not establish OEM maximums, actual power, available site capacity or supported configurations. The selected complete equipment and site must establish both cooling interfaces, the released physical work package and its separately owned acceptance outcomes. No timing model is used.

Common questions_

How many racks do I need for a GPU cluster?

The selected scenario supplies an assumed GPU count per rack. The tool divides the entered GPU count by that assumption, rounds up and retains a minimum of one rack group. For example, 8,192 divided by the NVL72 example's assumed 72 gives 114 groups after rounding. This is arithmetic, not a validated equipment population, rack elevation or supported OEM configuration.

How much power does a GPU cluster draw?

The tool multiplies the rounded rack groups by the selected assumed kW per rack, then multiplies that subtotal by 1.3 for an illustrative facility allowance. Those values are not measured draw, OEM maximum ratings or available facility capacity. The actual supplied-system power requirements and site allocation need their own applicable evidence and responsible review.

What does the cooling category establish?

Only the planning category for the selected example. NVIDIA's named DGX GB hardware guide describes liquid cooling at CPU and GPU cold plates, while other compute-tray components such as networking and storage use fan-driven air cooling; its power shelves also contain air-cooled PSUs. That named architecture does not approve every OEM arrangement. Confirm the exact system's complete air and liquid interfaces with its appointed equipment and facility owners; rack density alone supplies no universal cooling crossover.

Can this tool estimate a deployment schedule?

No. GPU count and a planning platform do not supply the released work package, dependencies, site access, crew calendar or defined acceptance milestone. Separately agreed physical IT installation and records do not include liquid-side work or full system commissioning. The appointed OEM, facility, cooling and systems parties retain their own outcomes and acceptance responsibilities. Build the schedule around those released inputs and the actual agreed scope; use the linked deployment-timeline guide.