04 / Responsibility Guide
Liquid Cooling Responsibilities & IT Installation_
Leviathan does not perform liquid-cooling installation, connection, handling, testing or commissioning. This educational guide helps customers distinguish OEM/cooling-contractor responsibilities from the separately agreed physical IT installation around a supplied system.
Physical IT scope only — no Leviathan liquid-side work
Assign the Cooling-Side Owner_
The customer must identify who owns the cooling design, facility interfaces, installation, procedures and acceptance for the actual equipment. Use the approved OEM and facility package rather than generic rack-power or temperature figures.
The responsible OEM and qualified cooling/facility contractors define the system-specific requirements and authorized work. This page is a responsibility guide, not a design, a procedure or a Leviathan cooling-service offer.
An IT installation schedule should identify these dependencies and who confirms readiness. Leviathan coordinates only its agreed physical IT work and does not assume cooling-side responsibility.
Cooling Tasks Assigned to Other Parties_
CDU Installation & Commissioning
The customer assigns the OEM/qualified cooling contractor to CDU placement, facility connections, controls and commissioning. Leviathan does not install, connect or validate CDU operation.
Manifold & Hose Work
Design, routing, installation and checks of supply/return manifolds and hoses belong to the responsible OEM/cooling contractor. They are not part of Leviathan physical IT cabling.
Liquid-Side Connections
The responsible OEM/cooling contractor selects and handles fittings and quick-disconnects according to the approved equipment procedure. This guide gives no generic connection, torque or seal-check instruction; Leviathan does not handle them.
Leak Detection & Monitoring
The customer assigns the responsible contractor to the required detection systems, monitoring interfaces and validation. Leviathan does not install or test cooling-side leak detection.
Pressure Testing & Flushing
Any required pressure checks, flushing and associated safety procedures are defined and performed by the authorized cooling professionals. Leviathan performs none of these tasks.
Coolant Fill & Flow Work
Fluid selection, fill procedures, flow checks and balancing belong to the OEM/cooling contractor for the specific system. Leviathan does not supply, handle or commission coolant.
Thermal Acceptance
The customer and responsible OEM/cooling specialists define and perform thermal commissioning and acceptance. Physical IT completion by Leviathan does not establish cooling performance.
System-Specific Requirements_
Request the approved equipment/cooling package from the responsible parties. It should identify the actual system configuration, required facility interfaces and the owner of each cooling task.
Do not infer generic water conditions, CDU capacity or rack ratios from this page. Those decisions require the actual design and the responsible professionals.
Provide the physical IT installer only the installation boundaries and readiness information relevant to its authorized work.
Cooling design, sizing, water-quality validation and mechanical acceptance remain with the responsible OEM/facility/cooling specialists; Leviathan does not certify them.
Understand the heat path before assigning a work package
Direct-to-chip cooling moves heat from selected electronic components into liquid through cold plates. In the arrangement described by the public ASHRAE 2023 Handbook, a technology cooling system carries heat from the IT equipment back to a CDU heat exchanger associated with the facility-water system. Rack manifolds distribute the supply and return paths. This is a conceptual explanation of that arrangement, not a piping diagram or a rule that every product has the same loops. [A1]
These names describe functions, not appointments. A CDU, a rack manifold and a server cold plate are not interchangeable pieces of a single IT-cabling task. A customer must identify the actual supplied equipment, the interface drawing and the responsible party for each package. A cable installer seeing the same rack does not acquire responsibility for its liquid interfaces.
The distinction also explains why a component's cooling description does not settle the room's entire heat-removal requirement. Use the particular system's documentation to identify which components use liquid and which use air; do not infer a universal percentage or eliminate an environmental requirement from the phrase direct-to-chip. The approved OEM and facility package governs the actual design.
| Interface or component | Conceptual function | Responsibility to resolve |
|---|---|---|
| Cold plate at an electronic component | Transfers component heat into its cooling path. | OEM and appointed cooling parties establish the applicable equipment and authorized work; no Leviathan liquid-side task. |
| Rack supply and return manifolds | Distribute the rack's liquid paths. | Name the supplier and qualified installer, interface boundary and required return; an IT-cable label is a different item. |
| CDU in the cited liquid-to-liquid arrangement | Transfers heat between the technology and facility sides. | Name the CDU, facility-interface, controls and commissioning owners; do not infer them from a rack-delivery line. |
| Agreed physical IT installation | Records the authorized rack-equipment and IT-cabling work. | Retain its particular permitted tasks and handoff; it does not include the liquid-side functions above. |
A conceptual scope comparison, not a technical design, supplier appointment, construction specification or connection sequence. The actual configuration can have different boundaries.
Use the named Rubin configuration to read the interface boundary
NVIDIA's DGX Vera Rubin hardware guide identifies rack liquid-cooling manifolds and describes cold plates on CPUs, GPUs and various networking and storage components in its compute trays. The DGX GB rack guide separately describes CPU/GPU cold plates with other compute-tray networking and storage components air cooled. Those are descriptions of the named systems, not a reason to copy a previous generation's cooling assumptions into another equipment package. [R1, G1]
For a Rubin physical-integration request, identify the complete ordered OEM system and delivered state before assigning the work. The presence of an internal manifold in the product description does not identify the site's CDU arrangement, its facility connection, cooling acceptance owner or an installer permitted to handle it. Equally, a facility cooling package does not identify which IT ports, equipment identities and permitted physical tasks belong in the IT installer’s handoff.
The buyer's coordination decision is therefore an interface decision: which supplied assembly and document revision does each party's work cover, and what return must the next party receive? Keep the OEM integration requirements, customer-appointed cooling work and separately agreed physical IT tasks visible. Leviathan's existing exclusion of all liquid-side work applies to this named context as well; a new GPU generation does not expand that offer. This guide supplies no handling, fluid, electrical, installation or operating method.
Separate capacity, monitoring and completion in the scope review
A facility capacity statement and a rack acceptance record answer different questions. A capacity statement describes a defined facility or cooling-system capability and its stated basis. It does not show that the identified installed rack configuration was examined under the agreed acceptance scope, or that the responsible party accepted its results. Ask the cooling owner for the applicable configuration, requirements and acceptance return rather than renaming a facility capacity sheet rack acceptance. The physical IT completion record remains a third, separate return.
Monitoring needs an equally explicit boundary. A device or cooling package can provide detection or measurement information without identifying who receives it, interprets it and owns the response. Name the equipment/signal owner, the monitoring recipient and the operational decision owner for the actual project. An IT installation record does not establish that this chain exists, and a reading in a dashboard is not itself a cooling acceptance result. This page gives no alarm setpoint, controls integration, leak response, sensor test or operating instruction.
Fictional EX-LC153 reviews three proposed scope lines for one supplied system. Two lines name proposed responsible parties; one leaves monitoring ownership unresolved. These are proposed assignments and requested outputs, not executed contracts, observed work or proof that the named parties are qualified. There are three lines, two proposed owners, one unassigned owner and zero completed checks or accepted results.
Use that distinction to prevent scope creep in an educational SOW discussion. Describe the actual task and its output rather than a broad phrase such as complete rack installation. If a new request adds a liquid connection, a detection-system task or responsibility for an alarm, return it to the customer and applicable specialist owner for an explicit scope decision. Do not turn coordination, a component label or the word cable into an unagreed trade duty. Actual contractual changes and acceptance remain with the authorized project parties.
| Fictional proposed scope line | Proposed owner and requested output | What remains separate |
|---|---|---|
| LC-IT: identified permitted rack-equipment and IT-cabling tasks | IT party I: item/connection identity record and physical exceptions for the agreed tasks. | No liquid fittings, detection validation, cooling acceptance or system-performance result is included. |
| LC-C: supplied CDU/manifold cooling package | Customer-appointed cooling party C: applicable configuration and its separately defined specialist completion/acceptance return. | Qualification, actual procedures, installed applicability and results are not supplied by this example. |
| LC-M: cooling detection/measurement information and monitoring handoff | No owner yet assigned for the equipment-to-monitoring-to-response boundary. | Customer/OEM/facility parties must resolve the owner, recipient and required return; neither I nor C is silently assigned the gap. |
Three fictional scope lines; two proposed owners, one unassigned boundary, zero completed checks, measurements, accepted results or work permissions. No contract template or legal entitlement is created.
Primary references and scope
- A1: ASHRAE 2023 Handbook, Chapter 20: direct-component cooling and TCS/CDU arrangement — Public conceptual description of cold plates, technology/facility loops and CDU/manifold functions only. No numerical design, fluids, piping, monitoring method, standards adoption, operating instructions or universal complete-system cooling claim. Checked 2026-10-19.
- R1: NVIDIA DGX Vera Rubin hardware: named compute-tray cooling components — Named rack/manifold and CPU/GPU/networking/storage cold-plate description only. No product availability, fluid/power value, installation/operating method, monitoring outcome or site compatibility approval. Checked 2026-10-19.
- G1: NVIDIA DGX GB rack hardware: named compute-tray liquid and air cooling boundary — Named CPU/GPU cold plates versus other networking/storage air cooling only; no universal percentage, transferred Rubin design, actual fluid/thermal requirement or field method. Checked 2026-10-19.
Responsibility & Readiness Handoff_
Name the Responsible Parties
The customer identifies the OEM, cooling/facility contractors and the owner of cooling acceptance.
Confirm the Approved Requirements
Those responsible parties define the equipment-specific cooling package, interfaces and procedures; Leviathan does not approve them.
Define the IT Work Boundary
Separate authorized rack equipment/IT cabling tasks from all liquid-side and facility work.
Record Readiness Dependencies
The customer supplies the other parties' readiness status and work-window constraints for the physical IT plan.
Keep Handoffs Separate
Cooling acceptance remains with its responsible specialists; the IT handoff records only the contracted physical installation and checks.
Coordinate Without Performing Another Trade_
The customer aligns facility/cooling readiness and physical IT installation windows. Name the contacts and dependencies so the work package identifies what may proceed and what requires confirmation from another party.
Leviathan may record the readiness status supplied by those owners for its IT installation plan. It does not validate mechanical drawings, flow capacity, water quality or CDU connections, and does not perform facility MEP work.
Requirements & Service Boundaries_
The responsible parties define approved system requirements and any applicable standards/procedures. This guide does not claim that Leviathan designs, certifies or commissions the cooling installation.
Equipment-specific pressures, temperatures, fluids and connection methods must come from the approved package and authorized personnel. No operational liquid-side instructions or universal platform values are supplied here.
Leviathan boundary: Physical IT installation only; no liquid-side design, installation, handling, tests or commissioning or licensed/facility engineering offer.
Project coverage: We support data center projects across the United States, subject to project scope, site requirements and team availability.
Separate Readiness & Acceptance Records_
The customer collects cooling-side readiness and acceptance records from the responsible OEM/cooling/facility parties. The agreed physical IT handoff separately identifies installed items, completed checks and remaining dependencies.
No customer-site history, cooling project totals, named-facility proof or OEM partnership is claimed by this guide.
Cooling Responsibility FAQ_
Does Leviathan install or commission liquid cooling?
No. Leviathan does not install CDUs, manifolds, hoses or cooling loops, connect liquid-side fittings, fill/flush systems, perform leak/pressure checks or conduct thermal commissioning. Those responsibilities belong to the customer, OEM and qualified cooling/facility contractors.
Who owns cooling requirements and acceptance?
The customer must assign the responsible OEM, cooling/facility professionals and acceptance owner. They define the approved requirements, procedures, safety controls and cooling-side acceptance records for the actual system.
Does physical IT coordination include handling cooling fittings?
No. Coordination records dependencies and work boundaries. It does not authorize Leviathan to handle hoses, quick-disconnects, manifolds or other liquid-side components.
What information should the IT installation team receive?
The customer should provide the approved physical work package, the responsible cooling/facility contacts, required readiness status and the permitted installation boundaries. Leviathan does not certify water quality, cooling capacity or mechanical readiness.
Can Leviathan discuss the physical IT work around a supplied system?
Yes, within an agreed scope for customer-supplied rack equipment, approved IT cabling and physical checks. Handling, any permitted cord task and instrument methods are separately reviewed. Tell us about your project, and our team will follow up to discuss the scope, requirements and availability.
What does direct-to-chip mean for an IT installer?
It describes a heat path using cold plates at selected electronic components and liquid cooling infrastructure. It does not turn the CDU, manifolds, hoses, controls or cooling acceptance into physical IT cabling. Identify the actual OEM system and appointed specialist boundaries; Leviathan performs no liquid-side work.
Why is facility cooling capacity not a rack acceptance test?
A capacity statement concerns its defined infrastructure and basis. It does not demonstrate the identified installed rack configuration's results under an agreed acceptance scope. Obtain the responsible cooling party's applicable configuration and acceptance return, separately from the physical IT handoff; this guide prescribes no test or pass criterion.
Is cooling monitoring automatically the IT installation team's responsibility?
No. The customer must resolve the actual equipment/signal owner, monitoring recipient and operational decision owner with the applicable OEM and facility/cooling parties. EX-LC153 deliberately leaves that boundary unassigned rather than assigning it through an IT record or a broad installation line. No monitoring integration, sensor test or response procedure is supplied.
Discuss the Physical IT Scope_
Tell us about your project, and our team will follow up to discuss the scope, requirements and availability.
Discuss a ProjectEmail Project Scope