Field Guide
GPU Cluster Acceptance Testing: Review the Evidence
A report marked pass is useful only when its scope matches the result you are accepting. Review which system was tested, what the evidence covers and who can accept it. A physical QA and installation handoff record, node diagnostic and cluster workload result answer different questions. Use this guide to review the submitted package; use the acceptance-test-plan article to define the requirements and methods before testing.
01
Identify the result being accepted
Scope and accepting party
- Start with the delivered system and the result the report claims: a mounted equipment package, installed cable plant, node diagnostic, fabric measurement or application outcome. A project name cannot define the coverage of each result.
- Match the report to the approved acceptance item, equipment identifiers and document revision. Use the acceptance-test-plan article to define requirements and methods; this guide addresses whether the submitted evidence answers them.
- Name the party authorized to accept that result and identify any separate facility, OEM or platform decision. Receipt of a report and acceptance of its covered work are different record states.
- Read exclusions and untested items before the summary status. A package can complete its agreed physical installation while a separate system-validation item remains open; record both states accurately.
02
Check physical installation evidence on its own terms
Installed work and physical records
- For the physical handoff, look for the agreed equipment positions, endpoint identifiers, installation records and unresolved defects. Reconcile the submitted evidence with the actual approved physical package, not a generic cluster-ready statement.
- If a report says a cable is certified, identify the exact links, instrument, personnel, method, acceptance criteria and report coverage. A label photograph or connectivity observation cannot supply a missing formal measurement report.
- Keep facility electrical, liquid-side and structural acceptance with the responsible qualified parties. Do not ask the physical installer to adopt an unrelated test result merely to fill an empty sign-off cell.
- Leviathan delivers inspection, cable identification, labeling checks, physical connectivity checks, defect recording and handoff documentation; formal procedures are planned with their equipment, method and criteria. [L1]
03
Read diagnostic coverage before reading pass
Named product, selected tests and limits
- Ask which systems and devices were included, which tests were selected and whether any item was skipped, excluded or interrupted. Keep the complete result and configuration with the summary rather than relying on a screenshot of one successful line.
- NVIDIA separates a quick health check and a pre-flight test in its DGX B200 guidance, and names the required installation parties for that product. A report should identify its actual system and applicable OEM instructions. [N1]
- NVIDIA states that DCGM Diagnostics are not designed to provide comprehensive hardware diagnostics, replace its field diagnosis tools or facilitate an RMA. Review the selected tool and test coverage without treating their pass status as a guarantee about every component or workload. [N3]
- Where the contract asks for application or integrated-system acceptance, request that separately defined evidence from its responsible owner. A node diagnostic report alone does not answer a different acceptance item simply because both mention the same GPUs.
04
Compare performance results with matching context
Metric identity and measurement coverage
- For a collective-performance report, identify the tool and version, collective operation, participating nodes and GPUs, message sizes, relevant software/configuration and result units. Ask the platform owner which agreed reference and criterion the result is being compared with.
- The official nccl-tests documentation distinguishes algorithm bandwidth from bus bandwidth; the bus-bandwidth conversion depends on the collective operation. Preserve the metric name when reading a result instead of treating an unlabeled bandwidth number as a measured rate for every physical port. [N2]
- Illustrative comparison: one submitted result covers an intra-node operation and another covers a multi-node collective. Ask the reviewer to reconcile the different test coverage before comparing them. This is a hypothetical report question.
- For thermal or sustained-load evidence, ask for the authorized workload, test window, monitored system, agreed criteria and responsible reviewer. The qualified OEM, platform and facility parties determine the actual method; this guide supplies no universal duration, temperature or fault threshold.
05
Resolve exceptions against the tested configuration
Disposition, retest and scoped acceptance
- Keep failed, missing and untested results distinguishable from accepted items. An exception needs the affected acceptance reference, evidence, responsible owner and disposition. Do not remove an unfavorable result when a later report is issued.
- If equipment, firmware, topology or the work package changed, ask the responsible reviewer whether the earlier evidence still covers the delivered configuration. The reviewer defines any affected retest scope; a newer report date does not answer that question.
- Ask the issuing party to link corrected work and retest evidence to the original exception. Preserve the configuration, report revision and decision so operations can understand what was actually accepted and what remains conditional.
- Record the accepting party, covered result, revision and open conditions through the project’s agreed process. A physical handoff is not a universal authorization for production; facility, OEM, platform and application decisions remain visible with their owners.
06Report
What the report must identify
| Report statement | Evidence to review |
|---|---|
| Installed | Approved equipment/endpoint identifiers, physical records and agreed checks for the actual installation package. Identify any absent record or unresolved defect. |
| Diagnostics pass | Named tool/version, included devices, selected tests, complete output and skipped or excluded items. Confirm the diagnostic’s documented limits. |
| Fabric healthy | Covered topology and links, observation period, reported events and the platform owner’s agreed interpretation. A link-up screenshot is only the evidence it actually shows. |
| Bandwidth in range | Named metric, units, collective, message sizes, participating resources, configuration and the agreed reference. Keep the raw result with its context. |
| Load test complete | Authorized workload and test window, covered system, report and criteria from the responsible OEM/platform/facility parties. No generic soak duration is assumed. |
| Retest cleared | Original exception, changed input or correction, affected coverage and the reviewer’s disposition linking the revised result to the delivered configuration. |
| Accepted | Named accepting authority, the specific result and report revision, exclusions and any open conditions. Keep separate acceptance decisions identifiable. |
This original review table supplies documentary questions, not technical test criteria. The responsible qualified parties determine the applicable method, thresholds, scope and acceptance authority for the actual project. The cited NVIDIA examples were checked on October 15, 2026.

07
Questions
Does a passing GPU diagnostic accept the whole cluster?
Does Leviathan run full GPU cluster acceptance and burn-in testing?
What if the report passes but covers a different configuration?
Contact
Discuss the physical verification package
Share the system models, site location, agreed physical tasks and requested handoff records. Our team will follow up to discuss scope, requirements and availability.