Buyer's Guide
Who Deploys GB200 and GB300 NVL72? Assign the Work Before Choosing the Team
An NVL72 deployment needs named owners for the purchased system, site infrastructure, physical installation and software acceptance. Those responsibilities may sit with one contracted provider or several teams. Select the arrangement from the actual equipment and service package; an OEM, integrator or internal-team label does not establish what is included.
Identify the purchased system and service package
Start with the order and delivered configuration. Record the manufacturer, complete system designation, rack identifiers, included components, shipment state and services purchased with it. Ask the supplier which activities have already been completed and which remain at the destination. A quotation for installing delivered equipment is different from one that includes assembling or integrating it before shipment.
NVIDIA's DGX GB Rack Scale Systems User Guide covers DGX Grace Blackwell systems including GB200 and GB300. That stated scope does not make it the installation authority for every OEM implementation using the same platform name. Record the exact documents applicable to the purchased system and resolve conflicting instructions with its responsible supplier. The guide's safety section gives product-specific documentation precedence and calls for technically qualified integration and service personnel.
Do not substitute a component name, a product photograph or an example architecture for that package. For a comparison of bids, ask each bidder to mark the same configuration revision. If the supplier changes the delivery state, revise the task allocation before retaining the old crew assumptions.
Evaluate the engagement, not the company category
There is no reliable rule that an OEM crew does only initial power-on while an integrator performs everything afterward. NVIDIA describes Infrastructure Services spanning planning, preparation, deployment, testing, training and handover. That is evidence of NVIDIA's published service range, not proof that a particular equipment order includes those services or that another firm has the same remit.
Use the supplier's proposal to establish the purchased boundary. Then ask which remaining tasks the facility, the customer's platform team or a physical installation provider will own. An internal team may retain overall acceptance while buying a bounded installation package. An integrated provider may coordinate several disciplines, but its actual subcontracting, permissions and responsibility allocation must be confirmed in the engagement.
A partner badge, certification or case study is useful only for the claim it actually supports. Ask how the proposed personnel and authorization relate to the named product and assigned activity. Do not infer a universal NVIDIA installation certification, customer relationship or warranty entitlement from a company's marketing category. Commercial and warranty questions belong with the relevant supplier and advisers.
Put the unassigned interfaces in one record
The useful comparison is not the number of disciplines on a provider's website. It is whether each necessary work package has an accountable owner, a defined starting condition and a receiving reviewer. The worksheet below is an original buyer aid. It does not prescribe which company must perform a task or authorize work on a live system.
For each row, put the actual organization and role beside the evidence reference. Mark unresolved items explicitly. A drawing can show a destination rack position without proving that the facility has released access. A delivery receipt can account for equipment without establishing its condition after integration. Keep these distinctions visible when comparing proposals.
Scroll the table horizontally on smaller screens.
| Work package | Evidence to request | Question that remains until assigned | Source |
|---|---|---|---|
| System supply and delivery state | Order configuration, shipment inventory and included services | Who confirms the delivered system matches the configuration used for planning? | Planning analysis |
| Receiving and physical preparation | Agreed custody points, condition record and discrepancy owner | Who decides what happens if an item is missing or its condition is disputed? | Planning analysis |
| Rack integration and destination installation | Supplier-approved task boundary, applicable documents and installation records | Which work is completed before arrival, and which work is authorized at the site? | Planning analysis |
| Facility and liquid-side interfaces | Required site releases and the responsible specialist contacts | Who owns readiness and acceptance at the interface to the delivered equipment? | Planning analysis |
| External IT cabling | Approved endpoint schedule, identifiers and defined verification outputs | Where does the physical connection record end and network configuration begin? | Planning analysis |
| Hardware validation and software readiness | Separately agreed plans, configuration records and result owners | What does each result cover, and who accepts the next stage? | Planning analysis |
| Final handover | Completed records, exceptions and named receiving team | Which unresolved item prevents which specific acceptance? | Planning analysis |
Illustrative planning fields, not an OEM installation sequence, safety procedure, contractual allocation or acceptance standard. Exact responsibilities must be agreed for the project.
Separate installed, validated and ready for workloads
NVIDIA's version 2.0.0 Mission Control management-plane and rack-setup checklist separates physical prerequisites, software and network configuration, firmware, documentation, performance validation and final acceptance. These are different evidence groups within that document's specified deployment context. An installation photograph cannot substitute for a software result simply because both appear under a deployment heading.
Use separate result records for the physical build, any agreed hardware-validation scope and the platform team's software or workload acceptance. Record the equipment identity, relevant configuration, test-plan reference, responsible executor, reviewed result and exceptions. The specific method and limits belong in the applicable approved plan; this article supplies neither.
Where a proposal includes burn-in, ask what hardware and configuration are covered, which plan governs the activity and who disposes of a failure. Do not infer duration, workload, environmental limits or production readiness from the word burn-in. Likewise, installation completion does not transfer BIOS, firmware, IP configuration or OS imaging to the physical crew unless an authorized, separately defined scope actually does so.
References: [N4]
Compare two proposals with different finish lines
Illustrative example EX-NVL-11: a buyer has ordered two racks and requests a deployment quotation. Proposal A includes destination placement, agreed external IT cabling and installation records. Proposal B includes those tasks plus a separately described platform-validation package. Neither price can be judged from the phrase complete deployment alone. The rack count is invented for this example and is not a Leviathan project record.
The buyer first checks the supplier's delivery package. If an activity is already included there, identify its owner and evidence rather than silently pricing it twice. Next, identify any missing facility release and the team that must supply it. Finally, compare the deliverables from A and B against the customer's actual acceptance needs. A lower-priced physical package may be appropriate if the platform team already owns the remaining work; it is incomplete if nobody does.
Suppose the cabling record identifies the installed endpoints but the platform team has not accepted network configuration. Record physical cabling and network acceptance as separate states. Do not relabel the whole system ready or treat the outstanding software result as proof that a cable is defective. Assign the open question to its owner, with the evidence needed for that decision.
Resolve specialist work before the site window
Keep electrical energization, liquid-system work, heavy handling and system commissioning with the appropriately qualified and authorized owners. Ask for the product and site documents governing the proposed activity and the written responsibility boundary. A statement that someone has deployed GPU hardware before does not resolve these assignments.
Do not use a generic pressure, coolant recipe, optical-loss number, command output or elapsed-time estimate as a substitute for the exact approved method. Nor should an instruction from a different rack or software version be carried into this engagement merely because the equipment names look similar. Document questions for the OEM, facility or platform owner before committing the affected field activity.
The buyer can still move independent preparation forward: reconcile the inventory, confirm which drawings will be used, agree identifiers and collect the intended handoff fields. The schedule should show the actual dependency. It should not hide an unassigned specialist task inside a promise that the installation crew will work it out on arrival.
References: [N3]
Bring a defined physical package to Leviathan
Leviathan can discuss the physical installation, rack assembly, structured cabling and documentation package for the proposed equipment and site. Send the system and rack list, delivery state, drawings, site access requirements, supplier responsibilities and requested handoff outputs. Identify any missing component, uncertain interface or activity whose owner has not yet been assigned.
BIOS, firmware, IP configuration, OS imaging and complete software commissioning are not standard Leviathan services. Liquid-side procedures and facility electrical work require their own responsible specialists. A scoped physical engagement does not imply NVIDIA authorization, an OEM partnership or acceptance of the whole system.
Use the conversation to define the physical work and required records. Actual handling, powered checks or instrument-based verification depend on confirmed resources, applicable methods and authorization for the engagement. Agree those conditions before treating the proposed package as executable.
References: [L1]
Common planning questions
Who should lead a GB200 or GB300 NVL72 deployment?
Name the party accountable for the contracted overall outcome, then assign the underlying tasks and acceptance owners. The purchased system and service package determine the split; an OEM, integrator or internal-team label does not settle it.
Does the OEM crew always stop after initial power-on?
No universal boundary can be inferred. NVIDIA publicly describes services extending through validation and handover. Check the services actually purchased for the named system instead of assuming either a minimal or end-to-end engagement.
Does a hardware burn-in result establish that the cluster is production-ready?
It establishes only the result covered by its defined plan, configuration and review. Physical installation, hardware validation and software or workload acceptance need their own scope and accountable owners.
What should I send for a physical installation scope discussion?
Send the complete system and rack list, delivery state, drawings, site access requirements, included supplier services and desired handoff records. Identify outstanding specialist interfaces and unresolved ownership questions.
Primary sources
- [N1] NVIDIA Infrastructure Services: published service rangeChecked 2026-10-17. Public overview observed October 17; no document revision displayed. Supports service-range discussion only, not inclusion in an order, provider credentials or a Leviathan affiliation.
- [N2] NVIDIA DGX GB Rack Scale Systems User Guide: scopeChecked 2026-10-17. Page last updated September 17, 2026. DGX GB rack-scale scope including GB200 and GB300; not a universal OEM installation manual. No rack specifications or operational steps adopted.
- [N3] NVIDIA DGX GB Rack Scale Systems User Guide: safety informationChecked 2026-10-17. Page last updated September 17, 2026; opening text refers to DGX GB200. Only product-document precedence and qualified-person responsibility are used. Its generic electrical, handling and service procedures are not reproduced or generalized.
- [N4] NVIDIA Mission Control rack setup: deployment summary, version 2.0.0Checked 2026-10-17. Version-specific path, page last updated July 16, 2026. Used only to distinguish validation and acceptance categories. No topology, component count, software version recommendation, command, test limit or procedure is adopted.
- [L1] Leviathan rack-and-stack installation and handoff scopeChecked 2026-10-17. Supports physical work, required inputs, conditional methods and handoff boundaries only. This article does not restate the page's materials-supply exclusion or make a procurement offer. Product/site authority is confirmed separately.