What Is Commissioning Levels?_

They progress from basic visual and mechanical inspections to electrical, thermal, and network validation under controlled conditions. Each level requires documented sign-off before the next phase begins to isolate faults early. Final stages incorporate integrated cluster tests that exercise both intra-rack and scale-out connectivity.

Technical Details

Copper NVLink connections inside the rack are validated separately from MPO-based fiber scale-out networks. Push-pull connectors on QSFP, OSFP, and MPO interfaces are inspected for proper seating without torque application. Results from each level are recorded and retained for the handover package.

How Leviathan Systems Works with Commissioning Levels

Field crews perform these levels sequentially after rack assembly, structured cabling, and liquid cooling connections on H100 through Blackwell NVL72 deployments. Any failure at an intermediate level directs targeted rework on cabling or cooling loops before proceeding.