Platforms
H100 Installation Checklist: Prepare the Evidence Before Rack Work
A useful H100 installation checklist starts with the complete delivered system, its applicable OEM documents and the released site work. Identify the equipment count, rack locations, mounting hardware, external connection roles and the owner of each acceptance step. Keep physical installation records separate from OEM system checks and platform/software acceptance. H100 alone does not specify a rack, cable plant or commissioning procedure.
Freeze the complete delivered system
Start the package with the manufacturer's full server model, ordered options, H100 variant and GPU count. NVIDIA's H100 product table distinguishes SXM from the PCIe H100 NVL form factor. Its DGX H100 guide describes a complete eight-GPU system, while the HGX reference documentation describes a platform implemented in supported OEM systems. These are different levels of identity.
Attach the applicable installation and service documents with their revisions. Include the actual rail or mounting kit and the delivered network-adapter configuration. Record an asset identifier when available so the released plan can be reconciled with the equipment received. A supplier description that says H100 server is not enough to settle those details.
If the delivered configuration differs from the released package, give that difference to the responsible owner. Do not carry a prior model's rack position, cable map or support arrangement forward without checking whether it applies. The purpose is to establish which instructions and approvals govern the actual equipment, before any field procedure is chosen.
Read DGX prerequisites at the complete-system level
For a purchased DGX H100, start with the named DGX system requirements rather than an H100 GPU rating. NVIDIA's current DGX H100/H200 guide specifies eight GPUs and an 8U enclosure; its power table gives 10.2 kW maximum for the complete system. These are three different quantities: installed GPU population, enclosure height and a published system-power bound. The power figure is not measured operating demand or a facility circuit design, and the enclosure height is not an installed or service-clearance approval. None of these figures describes every OEM server containing H100.
The manufacturer's installation boundary is also a prerequisite. NVIDIA's quickstart asks the customer to give relevant site information to the Installation Partner and requires installation by NVIDIA partner network personnel or NVIDIA field service engineers. Confirm the actual appointed arrangement for the order before assigning the work. This is a source-specific requirement, not evidence that Leviathan or any bidder satisfies it, and not an interpretation of the customer's warranty or contract.
Use the existing evidence checklist below with those source-specific facts. The applicable hardware package needs the actual supplied system and mounting arrangement, a location whose cabinet, service-access, power and environmental interfaces have been reviewed by their responsible owners, an assigned installation team, and the external connection and material plan. The DGX guide says network cables and adaptors are not shipped with the system and ties supported choices to the installed adapter firmware. Receiving the server therefore does not, by itself, establish that the approved external connection package is available. The purchasing owner and appointed suppliers must settle that package; no sourcing or resale service is promised here.
Keep physical readiness separate from startup and system acceptance. The manufacturer also documents operating and diagnostic procedures, but this checklist does not reproduce them or turn them into work assigned to the physical installer. An applicable installation package identifies who performs those separate tasks and what state or evidence their work requires.
Scroll the table horizontally on smaller screens.
| Published fact or boundary | Useful planning conclusion | Conclusion it does not establish | Source |
|---|---|---|---|
| Eight GPUs in the complete DGX H100 system | Count complete systems from the selected configuration | A GPU target alone selects the entire cluster or its rack layout | [N10] |
| 8U enclosure; 10.2 kW maximum whole-system power | Use complete-system mechanical and facility-interface documents | Cabinet fit, permitted rack density, operating load or electrical design | [N10] |
| Required installation channel and relevant site information | Confirm the order's installation arrangement and responsible site inputs | Any independent physical contractor is authorized for all DGX tasks | [N7] |
| Network cables and adaptors are not included; supported choices depend on the installed adapter firmware | Identify the approved external connection package and its supply owner | A universal cable bill or permission to substitute media | [N10] |
Current official DGX pages checked October 19, 2026. Named-system facts only; no electrical, handling, mounting, cooling, software or test procedure is supplied. The earlier source records and their original checked dates remain unchanged.
Count systems before planning the rack
A GPU inventory is not a rack layout. As an arithmetic example, an equipment plan for 32 GPUs using only complete eight-GPU systems contains four servers: 32 / 8 = 4. The cited DGX H100 documentation provides a real eight-GPU server example. The hypothetical quantity of 32 is not a workload-sizing recommendation.
That calculation does not tell the team how many racks to use. The equipment schedule still needs the exact servers, switches, management devices, storage and other included hardware. Mounting compatibility, service space, facility constraints and the approved arrangement remain separate inputs. Do not convert the four-server inventory into a rack-density or electrical-load promise.
Use a simple equipment schedule with one row per planned asset or clearly identified repeated configuration: item identity, quantity, proposed location, document reference and unresolved owner question. Keep GPU quantity as a field within that record. This makes missing supporting equipment visible without inventing a universal switches-per-GPU or servers-per-rack rule.
References: [N2]
Separate the GPU target from the provisioned system count
A planning number can mean GPUs requested for a workload, GPUs to purchase, GPUs physically installed, or GPUs available to a particular job. Those are not interchangeable counts. Before converting a number into hardware, identify which quantity the requester means and who has established the workload and availability assumptions. This article supplies inventory arithmetic, not a workload-sizing model or an availability guarantee.
Once the hardware target and exact delivered configuration are fixed, count complete units. For a uniform eight-GPU DGX H100 population, the number of complete systems needed to contain at least G physical GPUs is the smallest whole number not less than G divided by eight. Installed GPU inventory is then eight times that system count. This is a purchasing-population calculation only; it does not show that the GPUs can serve one application together or that the resulting population is a supported cluster design.
Fictional EX-HC81 asks for at least 129 physically installed GPUs, with every purchased compute unit stipulated to be a complete eight-GPU DGX H100. Sixteen units contain 128 GPUs, so the stipulated minimum requires 17 complete units containing 136 GPUs. The seven-GPU difference is an arithmetic overage against the physical-inventory target. It is not seven independently deployable spares, reserved workload capacity, permission to depopulate a server, or proof of usable capacity for a job. If the requirement instead demands exactly 129 GPUs, that delivered-unit assumption cannot meet the exact total; the equipment and workload owners must resolve the requirement.
Do not round the same calculation again into a rack count. The 17 systems occupy 136U of server enclosures in total at the documented 8U per system, spread across whatever arrangement is actually approved. That aggregate excludes supporting equipment, reserved positions and access conditions. It does not describe one cabinet, establish a minimum number of suitable cabinets or approve any density. Likewise, being able to buy 17 systems does not establish an installation date, an OEM-supported topology or a successfully scaled training workload.
References: [N10]
Make the compute-rack density assumption explicit
NVIDIA's H100 DGX SuperPOD reference architecture illustrates why the rack count is conditional. Its System Design section describes a scalable unit of 32 DGX H100 systems and rack designs supporting one, two or four of those systems per rack to accommodate different data-center requirements. These are choices within that reference design, not a general rule that any cabinet or site can accommodate any of the three arrangements.
With 32 complete eight-GPU systems, the compute inventory is 256 GPUs. The table shows the arithmetic if each stated reference arrangement applies uniformly to the compute population. The result is the number of racks carrying those compute systems under that assumption. It is not the total cluster-rack count, and it is not a recommendation to choose the densest arrangement. The site and equipment owners must establish which arrangement, if any, is applicable.
The companion architecture chapter explicitly allows rack layout to change with local power and cooling distribution and shows supporting management equipment separately. It also says the supporting equipment's sizes and quantities vary with the models used. Consequently, two offers can contain the same 32 DGX systems and still require different compute-rack populations and different supporting space. Compare their exact equipment and interface basis rather than treating one rack total as an intrinsic property of 256 H100 GPUs.
For a real mixed layout, count the named systems assigned to each approved rack and reconcile their sum with the equipment inventory. Keep network, management and storage allocations visible, including any equipment that shares a compute rack. Racks reserved for future delivery and empty planned positions are different from installed compute inventory. Do not infer rack suitability, floor loading, cable reach or an accepted power and cooling design from this arithmetic.
Scroll the table horizontally on smaller screens.
| Uniform arrangement described in the reference | Complete DGX H100 systems | Physical GPU inventory | Racks containing those compute systems | Source |
|---|---|---|---|---|
| One system per compute rack | 32 | 32 × 8 = 256 | 32 ÷ 1 = 32 | [N8][N10] |
| Two systems per compute rack | 32 | 32 × 8 = 256 | 32 ÷ 2 = 16 | [N8][N10] |
| Four systems per compute rack | 32 | 32 × 8 = 256 | 32 ÷ 4 = 8 | [N8][N10] |
Derived arithmetic from the named H100 reference, not three observed installations or three universally permitted densities. Supporting racks, storage, switches, management systems and site restrictions are not determined by this table. No power, cooling, loading, clearance or cable design is performed.
Evaluate training scale beyond the server total
Server count describes how many compute boxes are present. It does not describe how a training job uses them, which devices and links form the compute domain, or whether storage and management can support the intended service. NVIDIA's H100 SuperPOD reference treats compute systems, compute and storage fabrics, management equipment and storage as parts of an integrated architecture. Its design discussion starts from the customer's workloads; its rack plan is not simply an enclosure count multiplied by a universal allowance.
A buyer should separate three decisions. First, the platform and workload owners establish the intended jobs, concurrent use, per-job GPU and memory needs, data and checkpoint requirements, and the operating conditions under which they will judge the service. Second, the appointed architecture owners establish the applicable compute, storage and management design and its supported population. Third, the physical plan locates the exact delivered equipment and external connections within the accepted facility interfaces. No amount of detail in the third decision validates either of the first two.
Consider two fictional planning returns for the same 32 complete DGX H100 systems. Return A assumes four compute systems in each of eight compute racks; Return B assumes two systems in each of 16 compute racks. Both contain the same 256 physical GPUs and the same 256U of server enclosures before other equipment is counted. Their different compute-rack counts do not demonstrate different training speed or readiness. The proposed fabric, storage, management and facility packages still need their own applicable design and acceptance. Conversely, matching server totals cannot prove that those packages are equivalent.
The useful comparison asks what is included and what has actually been demonstrated: the precise compute population, interconnect and storage design, management reachability and security acceptance, supported software basis, workload acceptance scope, and measured results under stated conditions if any exist. A published reference-design count is not a measured result for the proposed customer installation. This article supplies none of those results or a topology, bandwidth, availability or performance guarantee. Keep any unanswered architecture or workload question open rather than resolving it with a larger server total.
Release an installation package with evidence behind each item
A checklist should let the team distinguish a ready work item from a question awaiting an owner. Use a document reference and disposition for each line: ready under the released scope, awaiting evidence or changed since release. A checked box with no applicable configuration, reviewer or reference is hard to use when the delivery changes.
The following is an original evidence checklist for agreed physical work. It does not replace the manufacturer's installation instructions or the facility's approval process. Keep controlled site information in the project's approved repository; the table describes record types and does not ask for credentials or private customer documents to be published.
Scroll the table horizontally on smaller screens.
| Package item | Evidence or reference to retain | Question that must have an owner | Source |
|---|---|---|---|
| Delivered configuration | Exact OEM system, H100 variant/count, installed options and asset/order reference | Does the released package match the equipment? | Planning analysis |
| Rack location and mounting | Approved rack elevation, actual mounting-kit reference and service-access requirements | Who has accepted this location for this system? | Planning analysis |
| Facility readiness | Confirmation for the applicable system interfaces and site conditions | Which facility dependencies must be complete before the permitted work? | Planning analysis |
| External connections | Released endpoint map by port, role, cable identity and approved media | Who resolves a port, label or routing discrepancy? | Planning analysis |
| Receiving and access | Receiving authority, equipment availability, permitted access and separately approved handling arrangement | Who releases equipment and access for the scheduled task? | Planning analysis |
| Scope and acceptance | Assigned physical work, OEM/service obligations, separate platform checks and required completion records | Who accepts each result and closes open items? | Planning analysis |
Original evidence questions. No rack fit, handling method, electrical/cooling readiness, formal test method or system certification is established by this table.
Separate management and workload connection roles
The DGX H100/H200 component table lists a BMC interface for out-of-band system management separately from system-management interfaces and the cluster/storage network connections. The BMC guide describes hardware monitoring and control functions. The connection guide also makes management-network security a distinct concern. These documents support keeping management as a named workstream, rather than treating every network port as interchangeable.
For the actual system, the network/platform owner should release the endpoint and access plan. The physical package can then name which approved cable reaches each specified port. Cabling completion is one result; authorized management access and correct network configuration are different results. Do not put login credentials into a cable schedule or use a physical connectivity record as proof that the management network has been secured.
The worksheet below separates the roles without prescribing VLANs, addresses, switch configuration or a BMC setup procedure. The labels on the delivered equipment and its applicable port documentation control.
Scroll the table horizontally on smaller screens.
| Role | Record for the actual system | Acceptance boundary | Source |
|---|---|---|---|
| BMC / out-of-band management | Named hardware-management port, cable identifier and approved destination | Physical endpoint record; platform/security owner accepts access and configuration | Planning analysis |
| Host / operating-system management | Named host interface, cable identifier and approved destination | Do not substitute the BMC record for host access acceptance | Planning analysis |
| Cluster network | Actual adapter/port, endpoint, approved media and design revision | Physical handoff is separate from fabric configuration or workload validation | Planning analysis |
| Storage / in-band connections | Actual assigned interfaces and approved external connection plan | Keep role and ownership visible even if multiple services share a designed network | Planning analysis |
Original planning worksheet, informed by the cited DGX example. It does not allocate the same physical ports on every H100 OEM system.
Count the OOB device population before counting cable assemblies
The existing endpoint worksheet separates BMC from host, compute and storage roles. For a cluster physical-cabling package, also establish the complete population of devices that need an out-of-band connection. NVIDIA's DGX component table identifies a separate BMC RJ45 interface, and its H100 SuperPOD reference describes an OOB network connecting BMCs and other managed devices. Counting only GPU servers can therefore omit equipment that the management design includes. It does not follow that every delivered switch, PDU or storage device has an identical port or must use one universal connection arrangement.
Use one row for each approved physical management endpoint: device and asset identity, applicable hardware-management port, intended role, destination and destination port, cable or channel identity, specified media and assembly reference, route or length basis, governing design issue, supply status and the owner of unresolved inputs. Where a connection uses intermediate patching, preserve the endpoint-to-channel relationship rather than pretending each record equals one purchased assembly. Credentials, addresses and security configuration do not belong in this public example or a general cable checklist. The responsible network and security owners establish the private access and configuration requirements.
Fictional EX-OB82 has a known proposed population of 32 DGX BMC endpoints, six switch management endpoints and two management-server endpoints. The example stipulates one approved physical OOB endpoint for each listed device; that stipulation is not a claim about every device of those types. It yields 40 known endpoint records. The storage and power-management populations have not been supplied, so the complete cluster OOB total remains unresolved. The tally is neither 40 purchased cable assemblies nor proof that a particular management switch has sufficient ports, uplinks, resilience or security.
Reconcile that endpoint population with the actual device inventory and the approved destination map before treating the physical package as defined. Check that each specified cable or channel has a traceable device and port at both ends, a permitted material and route basis, and a stated completion record. Return missing destinations, unallocated materials and contradictory port identities to their owners. After the authorized physical work, record the actual endpoints, labels, changes and open items; physical completion still does not prove secured BMC access, correct host configuration or management-service availability.
Scroll the table horizontally on smaller screens.
| Device group in the example | Stipulated endpoint count | What the count does and does not mean | Source |
|---|---|---|---|
| 32 DGX systems | 32 BMC endpoints | Known physical endpoint records; not the fabric or host-management population | Planning analysis |
| Six switches | Six management endpoints | Example assumption awaiting actual model and destination applicability | Planning analysis |
| Two management servers | Two management endpoints | Example assumption, separate from compute-node quantity | Planning analysis |
| Known subtotal | 32 + 6 + 2 = 40 | Not a complete cluster total, switch selection or purchased assembly quantity | Planning analysis |
| Storage and power-management devices | Population not supplied | Keep the total open; do not silently enter zero | Planning analysis |
Original fictional endpoint-population example. No customer equipment, actual connection, secure access, continuity, topology, selected cable or completed physical work is asserted.
Include the OEM deployment boundary in the schedule
Check whether the purchased system has an OEM deployment or support requirement before assigning all tasks to an installer. For example, Dell's XE9680 manual lists its H100 configuration and states a requirement for ProDeploy Plus or Dell Customer Deployment services, with deployment GPU subsystem tests for applicable XE-series models. Confirm the actual order's arrangement with Dell.
For DGX H100/H200, NVIDIA's service introduction directs customers to its support process for replacement guidance and assistance installing or moving the system. A public document is not proof that a third party has been appointed for that work. Record the approved arrangement and the interface with any separately scoped physical team.
Schedule the physical handoff and the OEM/system checks as separately owned events. If the OEM or appointed team needs a particular condition or document, record that prerequisite in the work package. This guide does not offer instructions for internal GPU work, power-up sequencing, liquid-loop work, firmware changes or stress testing.
Assign four acceptance results
A single installed status can hide different open questions. Track the facility release, physical completion, OEM/system disposition and platform/software acceptance separately. Give each result an owner, the evidence it needs and the place where exceptions are recorded. The project's agreed acceptance process determines when each work package is complete.
For example, a label photograph may help establish where a cable was installed. It does not show whether the OEM accepted the server or whether the customer's model ran correctly. Conversely, an application result does not update an incorrect rack elevation. Keeping the evidence attached to the right result prevents those gaps from disappearing at handoff.
Scroll the table horizontally on smaller screens.
| Result | Assigned owner | Example evidence to define in scope | Source |
|---|---|---|---|
| Facility release | Appointed facility/design authority | Applicable location/interface confirmation and outstanding restrictions | Planning analysis |
| Physical installation completion | Authorized physical-work team and customer reviewer | Installed asset positions, mounting/cable records, labels and recorded deviations | Planning analysis |
| OEM / system disposition | OEM or appointed support/deployment team | Required OEM completion records and supported configuration disposition | Planning analysis |
| Platform / software acceptance | Customer platform and application acceptance owners | Agreed system/software checks and their separately defined results | Planning analysis |
Original division of evidence questions. No specific technical test, acceptance standard or contractor entitlement is implied.
Record the discrepancy before changing the plan
Illustrative exception: the receiving record identifies the expected H100 server model, but the adapter layout does not match the released endpoint map. The physical team can identify the discrepancy, preserve the actual port/asset reference and ask the designated owner for a disposition. It should not silently select a different connection because the plug appears to fit.
The disposition might supply a corrected port map, confirm that the approved configuration differs or require a different customer-furnished component. Attach the approved revision to the work record before completing the affected task. Other work may proceed only within its own released scope and prerequisites.
This is a fictional documentation example. It is not a failure rate, a customer event or a claim that Leviathan routinely diagnoses H100 fabric faults. The useful outcome is a traceable connection between the observed issue, the responsible decision and the resulting as-built record.
Close a useful physical handoff
Prepare the agreed completion records around the actual assets and authorized work: equipment locations, applicable plan revisions, completed mounting and cable identities, approved changes and open items with owners. Include any agreed inspection or verification results with their defined scope. Do not relabel visual inspection or physical connectivity records as formal cable certification, system commissioning or application acceptance.
Leviathan can discuss agreed rack-and-stack installation, physical mounting, structured cabling, routing, labeling and physical handoff documentation for customer-furnished equipment. The actual project scope, site requirements and team availability control. OEM-required deployment work, facility electrical/cooling responsibilities and platform validation must remain assigned to the appropriate owners.
A useful inquiry supplies the exact H100 system, quantity, site, planned installation window, customer-furnished equipment/materials, released rack/connection plans and the tasks requested. That gives the installation discussion a concrete work package without turning a general H100 checklist into an unsupported technical procedure.
References: [L1]
Common planning questions
Does an H100 GPU count tell us the rack count?
No. First identify the complete server configuration and equipment inventory, then obtain the approved layout and site/interface decisions. The arithmetic example converts a stated GPU quantity into a server inventory only.
Is an HGX H100 baseboard the same installation package as a DGX H100 server?
No. Identify the complete delivered OEM system, applicable documents, mounting parts and assigned work. The baseboard/platform name does not settle the rest of the server or rack configuration.
Does completed BMC cabling prove management access is secure?
No. A physical endpoint record and the platform/security owner’s access and configuration acceptance are different evidence.
Does Leviathan provide H100 system commissioning under this checklist?
This guide describes a physical installation evidence package. OEM/system checks, formal test procedures and platform/application acceptance must have separately appointed qualified owners and agreed scope.
Do 129 requested GPUs mean 129 GPUs can be ordered as complete eight-GPU systems?
Not exactly under that stipulated configuration. Seventeen complete eight-GPU systems contain 136 GPUs; 16 contain 128. The requirement owner must distinguish a minimum physical inventory from an exact total or workload demand. The arithmetic does not establish usable job capacity, spare availability or a supported cluster topology.
Does NVIDIA's 32-system H100 scalable unit always occupy eight racks?
No. The named H100 reference describes one, two or four DGX systems per rack to accommodate data-center requirements. For 32 systems those assumptions yield 32, 16 or eight compute-bearing racks respectively. They do not determine the supporting equipment space or authorize any arrangement at the actual site.
Can two clusters with the same DGX server count be treated as equivalent training systems?
No. The applicable compute, fabric, storage, management, software and workload acceptance basis must also be compared. A physical inventory or published reference-design count is not a performance or availability result for the proposed installation.
Does a subtotal of 40 OOB endpoint records mean the project needs 40 cables?
No. EX-OB82 counts stipulated known endpoints, with other device populations still missing. The actual channel, intermediate patching, destination map and approved assembly schedule determine the material package. Endpoint completion also remains separate from secured management access and configuration acceptance.
Primary sources
- [N1] NVIDIA H100 product specificationsChecked 2026-10-15. SXM and PCIe NVL form-factor distinctions only. No benchmark, price, performance, availability or universal rack/cooling assertion adopted.
- [N2] NVIDIA DGX H100/H200 user guide: introduction and componentsChecked 2026-10-15. Exact DGX H100 eight-GPU system and separate BMC, host-management, cluster/storage roles. No H100 NVL72 product or network media quantity inferred.
- [N3] NVIDIA HGX reference architecture: componentsChecked 2026-10-15. HGX baseboard/platform and complete OEM systems are different levels. No complete rack plan or mandatory topology inferred from the reference architecture.
- [N4] NVIDIA DGX H100/H200 service manual: introductionChecked 2026-10-15. Support ownership and assistance for installation/moving. No component replacement, handling, electrical, power-capping or stress-test procedure reproduced.
- [N5] NVIDIA DGX H100/H200 connection guideChecked 2026-10-15. Direct/remote console and separate BMC-management security concerns only. No default credentials, addresses, access instructions or firewall configuration reproduced.
- [N6] NVIDIA DGX H100/H200 BMC guideChecked 2026-10-15. BMC monitoring/control role only, not evidence of an actually secured/configured customer management network or a Leviathan software service.
- [D1] Dell PowerEdge XE9680 installation and service manual: GPU specificationsChecked 2026-10-15. Published H100 configuration and Dell deployment-services note. Actual customer order/services must be confirmed; no transfer of OEM obligations to Leviathan asserted.
- [L1] Leviathan rack-and-stack installation scopeChecked 2026-10-15. Agreed physical work for customer equipment, subject to project/site/resources. No GPU supply, internal component service, electrical/cooling work, certified testing, workload tuning or system commissioning inferred.
- [N7] NVIDIA DGX H100/H200 quickstart: Installation and ConfigurationChecked 2026-10-19. Only the relevant-site-information and required installer-channel paragraphs. No warranty interpretation, registration, command, startup, security, diagnostic or stress-test procedure reproduced.
- [N8] NVIDIA H100 DGX SuperPOD reference: key components and System DesignChecked 2026-10-19. RA-11333-001 V11, September22,2023; page last updated November19,2025. Named32-system scalable unit, one/two/four-system rack-design options, complete architecture categories and OOB scope only. No performance, deployment-time, bandwidth, security implementation or actual site suitability claim adopted.
- [N9] NVIDIA H100 DGX SuperPOD reference: architecture and adjustable rack layoutChecked 2026-10-19. Local power/cooling distribution can change rack layout; supporting management-equipment sizes and quantities vary with models. No reference rack diagram, power-density figure, switch/cable quantity table or actual facility design copied.
- [N10] NVIDIA DGX H100/H200 current complete-system specifications and external cable supplyChecked 2026-10-19. Current re-read of the existingN2 URL for these additional claims: eightGPUs,8U,10.2kWmaximum whole-system bound, separateBMCinterface and network cables/adaptors not shipped with supported choices tied to firmware. OriginalN2 record/checked date remain exact. No numeric airflow, dimensions, load, power connection, port-mapping command or operating procedure adopted.