Platforms
DGX GB200 vs DGX GB300: NVL72 Network Interfaces
For the named NVIDIA DGX systems, the September 17, 2026 hardware guide lists four single-port 400G OSFP ConnectX-7 NICs per DGX GB200 compute tray and four single-port 800G OSFP ConnectX-8 NICs per DGX GB300 compute tray. That difference requires an exact endpoint and cable-plan review; it does not establish cable reuse, achieved bandwidth or facility readiness.
Begin with the delivered system, not the generation label
This comparison uses the named NVIDIA DGX GB200 and DGX GB300 configurations in the DGX GB Rack Scale Systems User Guide, updated September 17, 2026. A supplier-specific rack built with the same accelerators still needs its own system documents. Start with the complete ordered system, not only the GPU or NVL72 name.
The tables explain three different comparison levels: NVL72 product populations, the named DGX compute-tray interfaces and one model-specific local port-map row. The fictional records then show how those facts change a requested connection package. Keep the quantity being compared attached to its level: a GPU count, a tray NIC count and a connection-record identifier are not interchangeable populations.
References: [N1]
Compare the rack population before inferring the physical change
NVIDIA's GB200 NVL72 product page lists 36 Grace CPUs and 72 Blackwell GPUs; its GB300 NVL72 page lists 36 Grace CPUs and 72 Blackwell Ultra GPUs. The GPU generation changes while the CPU and GPU populations stay the same.
The shared DGX guide identifies 18 compute trays, each with two Grace CPUs and four GPUs, plus nine NVLink switch trays and management switches. Eighteen times four accounts for 72 GPUs; eighteen times two accounts for 36 CPUs. Those are named-system tray populations, rather than shipping-package counts or a field conversion package.
The product pages publish 13.4 TB GPU memory for GB200 NVL72 and 20 TB for GB300 NVL72. These are rack-level product quantities. Rounded totals should not be divided into supposedly exact per-device figures or read as free workload memory. The DGX guide also describes liquid-cooled compute CPUs/GPUs and air-cooled components such as networking and storage. A rack-scale liquid-cooled label therefore does not mean every component uses the same cooling medium.
Use the correct comparison level for each question: product totals describe the NVL72 configuration; the DGX tables describe the named implementation; the ordered configuration and its approved interface package govern a physical project. The compute-tray NIC comparison provides a concrete changed attribute despite the unchanged GPU count.
Scroll the table horizontally on smaller screens.
| Comparison level | Published GB200 basis | Published GB300 basis | Boundary for a physical decision | Source |
|---|---|---|---|---|
| NVL72 product configuration | 36 Grace CPUs and 72 Blackwell GPUs | 36 Grace CPUs and 72 Blackwell Ultra GPUs | Same population does not mean the same supported components or system | [N5][N6] |
| Named DGX compute-tray inventory | 18 trays × 4 GPUs and 2 Grace CPUs | The shared guide gives the same tray population | Counts reconcile the named rack; they do not authorize a tray replacement or rack conversion | [N3] |
| NVL72 product GPU-memory total | 13.4 TB | 20 TB | Published rack-level quantities; not free workload memory, a unified allocation or exact per-GPU figures | [N5][N6] |
| Named DGX cooling description | Compute CPUs/GPUs liquid cooled; other components described as air cooled | The shared guide describes the same categories | Actual configured interfaces and conditions need separate applicability; no facility reuse approval | [N3] |
| External cluster-network hardware | See the compute-tray NIC comparison below | See the compute-tray NIC comparison below | The changed NIC generation and nominal rate require their own endpoint and approved-assembly comparison | [N1] |
Public product totals and the named DGX implementation are different source levels. The figures apply to the cited configurations; actual ordered interfaces and site applicability require their own evidence.
Read the cluster-network row at compute-tray level
NVIDIA's hardware table makes a specific distinction between the two compute trays. The entries below are per compute tray, not a count of all external connections in an installed rack. They describe interfaces, not measured application throughput or an approved cable assembly.
OSFP appears in both cluster-network descriptions. That shared form-factor label does not resolve the approved transceiver, cable construction, reach, breakout arrangement or remote switch endpoint. Keep those items as separately verified fields. A higher nominal port rate also does not demonstrate that the existing channel or the planned topology will deliver it.
References: [N1]
Scroll the table horizontally on smaller screens.
| Documented item | DGX GB200 | DGX GB300 | Source |
|---|---|---|---|
| Cluster-network NICs per compute tray | 4 × ConnectX-7, single-port 400G OSFP | 4 × ConnectX-8, single-port 800G OSFP | [N1] |
| Storage/management networking in the shared hardware table | 2 × BlueField-3 DPU, dual-port 400G InfiniBand or Ethernet | 2 × BlueField-3 DPU, dual-port 400G InfiniBand or Ethernet | [N1] |
| Out-of-band hardware interfaces in the shared table | Compute-tray BMC and BlueField-3 BMC RJ45 interfaces listed separately | Compute-tray BMC and BlueField-3 BMC RJ45 interfaces listed separately | [N1] |
Per-compute-tray descriptions in the September 17, 2026 DGX hardware table. These are documented interfaces, not achieved traffic rates or an approved assembly list.
Keep network role separate from the connector
The networking guide distinguishes compute communication, storage access, provisioning/management and out-of-band access. Its DGX GB200 and DGX GB300 tabs also provide separate interface-name maps. A cable schedule that collapses these into one generic network connection loses information needed by the customer and the installation team.
Record the physical port identifier and the intended network role together. Preserve the remote endpoint, assembly identifier and configuration reference on the same connection record. If software interface names are included, retain the system-specific map and its revision; do not assume a copied operating-system name still identifies the same physical endpoint.
The guide includes a general compute-port table labelled ConnectX-7 as well as model-specific material. This article uses the explicit GB200/GB300 hardware row for the generation comparison. For an actual job, an ambiguous or conflicting document needs a supplier or OEM clarification, rather than an installation team's interpretation of a nearby diagram.
Read the same physical port through both model-specific maps
The September 17, 2026 networking guide supplies separate Network Interface Names tables for DGX GB200 and DGX GB300. The literal rows below have the same physical designation and published PCIe bus entry, but different operating-system interface and RDMA names. A matching physical label therefore cannot validate every field copied from another model's map.
The uppercase P in the published GB300 string ibP18p3s0 is significant to this comparison and remains exact. These are document entries, not observed output from a customer's system. Bind the actual complete configuration to its applicable map before relying on a software name. The EX-PM95 record immediately below shows what a returned documentary correction can resolve while leaving the assembly and installed-state questions open.
References: [N4]
Scroll the table horizontally on smaller screens.
| Model tab | Physical port designation | Published PCIe bus | Published interface name | Published RDMA name | Source |
|---|---|---|---|---|---|
| DGX GB200 | Right Bay OSFP P4 | 12:03:00.0 | ibp11p3s0 | mlx5_5 | [N4] |
| DGX GB300 | Right Bay OSFP P4 | 12:03:00.0 | ibP18p3s0 | mlx5_3 | [N4] |
Literal September 17, 2026 model-specific entries, including capitalization. One local row per model; the table does not supply the remote endpoint or an observed installed map.
EX-PM95: compare one complete connection record
Fictional EX-PM95 has connection identifier E-27 for a planned DGX GB300 tray CT-03. Its first return, PM1, combines that requested model with the GB200 Right Bay OSFP P4 interface and RDMA names. The requested endpoint identity has not changed into another connection merely because two copied fields need correction.
For this example, stipulate that the appointed system owner returns configuration reference SYS-GB3-02 issue 2 and map MAP3/B for CT-03, and the network owner returns connection schedule CS9/B. PM2 associates E-27 with those returned issues. Its local map uses the published GB300 row, while its role and remote destination are separately supplied fictional planning fields. The NVIDIA row itself supplies neither the remote destination nor the assembly choice.
PM2 resolves the model-map association and records the requested role and destination. The approved assembly is still absent and no installed-state observation has been returned, so the physical connection package remains incomplete. Keep PM1 and PM2 together: the later return answers specific questions without turning a documentary correction into an observed endpoint or a technical operating result.
References: [N4]
Scroll the table horizontally on smaller screens.
| Field | PM1: copied return | PM2: owner-returned record | Source |
|---|---|---|---|
| Connection and requested item | E-27; DGX GB300 tray CT-03 | E-27; DGX GB300 tray CT-03 — same requested connection | Planning analysis |
| Configuration and map issues | SYS-GB3-02 issue 1; CS9/A contains the GB200 map row | SYS-GB3-02 issue 2; MAP3/B; CS9/B, stipulated owner returns | Planning analysis |
| Physical designation and published bus | Right Bay OSFP P4; 12:03:00.0 | Right Bay OSFP P4; 12:03:00.0 | Planning analysis |
| Interface and RDMA names | ibp11p3s0; mlx5_5 — GB200 document entries | ibP18p3s0; mlx5_3 — GB300 document entries | Planning analysis |
| Requested network role | Not identified | computenet, stipulated by the fictional network owner | Planning analysis |
| Remote endpoint | Not identified | SW-09 port P6, a fictional returned planning value | Planning analysis |
| Approved assembly and physical observation | Neither supplied | Still neither supplied; those questions remain open | Planning analysis |
All equipment/configuration, connection, remote-endpoint and issue identifiers in this record are invented. Only the two model-specific local map rows are quoted documentary data. No assembly compatibility, installed topology, permitted work or actual acceptance is established.
Resolve a copied schedule before treating it as an order
Consider fictional change record EX-GB-27. A project has replaced its DGX GB200 equipment line with DGX GB300, while a spreadsheet still describes the compute links as 400G ConnectX-7. Its cable assembly list has not changed, and the switch team has not signed off the new endpoint map. No hardware failure has been observed; the inconsistency exists in the released planning records.
The useful response is a documentary hold on the affected connection package. Ask the system owner to confirm the delivered configuration and the network owner to release the intended endpoints and approved assemblies. Keep unaffected work distinct if the customer authorizes it. Neither a blanket replacement order nor a blanket reuse statement resolves this particular mismatch.
Scroll the table horizontally on smaller screens.
| Record | Observed conflict | Required disposition | Source |
|---|---|---|---|
| Equipment line | New model names DGX GB300; network sheet retains ConnectX-7 wording | System owner confirms ordered configuration and applicable document revision | Planning analysis |
| Connection schedule | Port-role map copied from the old rack without review | Network owner releases exact local and remote endpoint identities | Planning analysis |
| Assembly list | Old part identifiers retained with no compatibility evidence | Responsible supplier/network owner identifies approved assemblies or records an unresolved item | Planning analysis |
| Work release | Ticket says reuse everything; design review remains open | Customer defines which physical tasks are released and which remain held | Planning analysis |
Fictional buyer analysis, not a real project, bill of materials, approved design or instruction to alter equipment.
Turn the connection-record changes into the right scope question
Several changed fields can describe one requested connection. In EX-PM95, E-27 remains the same requested connection across PM1 and PM2. Two local identifier strings change to the GB300 document entries, and the fictional owners supply the role and remote destination. Those field changes do not create several new physical links or count how many cable assemblies the project needs.
The next purchasing question is specific: which approved assembly and included physical connection work complete E-27's package? PM2 still lacks the assembly and any installed-state observation. A supplier return identifying the applicable assembly would answer a different question from MAP3/B's local name mapping; a later physical record would answer a different question again. The buyer can request the missing assembly disposition without reopening the already identified model-map relationship or ordering blanket recabling.
Use the same distinction in EX-GB-27: the changed model/NIC description identifies an affected connection package, while its endpoint and assembly returns determine what physical scope can actually be agreed. The connection comparison supplies no conclusion about a floor, power or coolant system. Those separate interfaces need their configuration-specific qualified decisions.
Compare what arrives integrated before comparing the remaining work
Fictional EX-RF96 contains one current DGX GB200 NVL72 equipment line and one proposed DGX GB300 NVL72 line. Its instruction to keep the existing rack because both names contain NVL72 leaves the delivery package unspecified. Separate two possible supplier returns rather than treating that instruction as a scope.
Return R-A identifies a complete replacement DGX GB300 system with its stated factory-integrated contents and separately listed customer-side external connections. On that stipulated return, the buyer can discuss the remaining authorized physical installation package around a defined delivered system. Treatment of the current equipment and the site's interfaces still need their own agreed scope; the supplier return is not evidence that those activities are included.
Return R-B says conversion but does not identify a supported modification package, supplied parts or permitted product-controlled work. It has not supplied the equivalent delivery boundary. Before comparing it with R-A, obtain the actual supported offer and included tasks from its responsible supplier. This example asserts neither that an in-place conversion exists nor that it is impossible. It explains why a quote for identified external work and an undefined internal modification are not yet prices for the same deliverable.
The table separates that supplier-delivery decision from external connection applicability, facility interfaces and final handoff. Once those returns identify the scope, the appointed project owner can define the actual work package. The network-interface facts alone cannot define a conversion method or accept an installed system.
Scroll the table horizontally on smaller screens.
| Decision in the fictional request | Evidence or return needed | Work conclusion still open | Source |
|---|---|---|---|
| Complete replacement or supported modification? | Exact offered system/package, supplied integration and permitted service scope | No in-place conversion or internal component reuse is approved | Planning analysis |
| Retain or change external connections? | Model-specific endpoint map, remote-port design and approved assembly applicability | No blanket recabling or blanket reuse decision | Planning analysis |
| Retain the location and facility interfaces? | Configuration-specific decisions from the appointed facility and qualified technical owners | No rack fit, structural, power, liquid or service-access approval | Planning analysis |
| What is handed over and accepted? | Defined physical records, open items and separate OEM/platform/workload acceptance responsibilities | No operational readiness, commissioning or performance result | Planning analysis |
One fictional current/proposed system pair and four decision categories. R-A and R-B are illustrative supplier returns, not actual offers or approved field tasks.
Release a traceable endpoint handoff
The installation package should identify what equipment and customer-furnished assemblies are available, which physical connections are in scope, and which drawings or schedules govern them. It should also distinguish installation records from separately produced technical verification reports. A tidy label photograph does not establish network configuration or workload acceptance.
At handoff, reconcile the agreed cable identifiers, local and remote endpoints, drawing revision and open defects. Record any approved changes against the released baseline. If an endpoint or assembly remains unresolved, identify it plainly so that the customer can decide the next action with the relevant technical owner. The aim is a usable record of the installed physical work, not a claim that a GPU generation has been commissioned.
Bring the configuration to the scope discussion
Leviathan can discuss agreed physical equipment mounting, structured cabling, routing, dressing, labeling, inspection, remediation and handoff documentation. The project must define its site conditions, authorized tasks, customer-furnished equipment/materials and available resources. Rack placement, handling and lifting need project-specific review.
Leviathan does not offer, coordinate or subcontract liquid-side work. Identify the appointed equipment/material supplier, approved configuration, quantities and delivery responsibilities before agreeing the physical work. Electrical installation, hardwiring, new circuits and energization remain excluded; full system/software commissioning is not a standard service. Formal testing requires separate confirmation of the actual equipment, personnel, method and acceptance criteria. Send the complete system configuration and the affected endpoint records so the physical scope can be discussed without inventing those approvals.
References: [L1]
Common planning questions
Does OSFP on both systems prove the old cable can be reused?
OSFP identifies a form factor, not the approved assembly or channel. Compare the specific endpoint, assembly and intended-mode evidence for E-27 rather than deciding reuse from that shared label.
Are the listed NIC counts rack totals?
They are compute-tray entries in the named DGX hardware table. Keep the four-NIC tray population separate from the rack population and the actual connection/assembly list.
Can a GB200 port map be copied into a GB300 handoff?
Use it as a comparison baseline. EX-PM95 keeps one connection identity across two returns while correcting the local map and recording the missing assembly and installed-state questions.
Does this comparison determine power or liquid-cooling upgrades?
The network comparison does not supply a facility-interface assessment. The ordered system’s power, cooling, structural and product-controlled service requirements need their own qualified owners and applicable documents.
If both NVL72 systems contain 72 GPUs, what changes in the comparison?
The product pages identify Blackwell versus Blackwell Ultra GPUs and different published rack-level GPU-memory totals; the named DGX hardware table also distinguishes cluster-network NICs. The unchanged CPU/GPU population does not establish identical interfaces, supported parts, delivered integration or a reuse decision.
Can the same physical port designation have different software and RDMA names?
Yes in the cited model-specific example. Right Bay OSFP P4 is listed with ibp11p3s0 and mlx5_5 for DGX GB200, but ibP18p3s0 and mlx5_3 for DGX GB300. Preserve the exact published model/issue and compare the actual configuration; these entries are not a command or a universal mapping.
Does a GB300 comparison provide an in-place upgrade path for an existing GB200 rack?
The public comparison does not identify a supported conversion package. EX-RF96 distinguishes a defined complete-system return from an undefined modification request so the buyer can compare actual delivery and remaining-work scopes.
Primary sources
- [N1] NVIDIA DGX GB Rack Scale Systems User Guide — HardwareChecked 2026-10-16. September 17, 2026 edition; explicit model-specific cluster NIC row and shared storage/management/OOB hardware descriptions only. No generic OEM equivalence, speed attainment, power, cooling or structural requirement adopted.
- [N2] NVIDIA DGX GB Rack Scale Systems User Guide — NetworkingChecked 2026-10-16. September 17, 2026 edition; network roles and separate model tabs. General ConnectX-7 port table is not treated as a GB300 map. No configuration method or public port-diagram reproduction.
- [L1] Leviathan Systems — Structured CablingChecked 2026-10-16. Published physical scope only; actual project tasks, formal testing resources and technical authority require agreement.
- [N3] NVIDIA DGX GB hardware: current rack and compute-tray configurationChecked 2026-10-20. September 17, 2026 shared guide re-read for 18 compute trays, two Grace CPUs and four GPUs per tray, nine NVLink switch trays, management switches, and liquid-cooled CPUs/GPUs versus other air-cooled components. No power/cooling values, operating, connection or service method, or OEM-wide reuse adopted.
- [N4] NVIDIA DGX GB networking: separate model-specific interface-name tablesChecked 2026-10-20. One exact Right Bay OSFP P4 row per model, preserving case, PCIe bus and RDMA name. This is read-only documentary comparison, not an observed endpoint, software change, command, complete map, remote destination or cable selection.
- [N5] NVIDIA GB200 NVL72 product configuration and GPU-memory specificationChecked 2026-10-19. Only the 36-Grace-CPU, 72-Blackwell-GPU NVL72 configuration and 13.4 TB published rack-level GPU memory. No benchmark, per-device calculation from rounded totals, workload capacity, price, availability or actual facility requirement inferred.
- [N6] NVIDIA GB300 NVL72 product configuration and GPU-memory specificationChecked 2026-10-19. Only the 36-Grace-CPU, 72-Blackwell-Ultra-GPU NVL72 configuration and 20 TB published rack-level GPU memory. No aggregation of fast, CPU and GPU memory, marketing performance, per-device rounding, price, provider availability or customer conversion eligibility inferred.