Installation
GPU Data Center Migration: Plan the Physical Handoff
Plan a GPU data center migration as linked source and destination work packages. The physical plan must preserve equipment identity and endpoint records while separate authorized owners control shutdown, facility interfaces, movement and return-to-service decisions.
Define the retrofit decision before requesting a move
An enterprise AI retrofit begins with a proposed equipment change and the services that must survive it. A move is one possible part of that change. Write down what is being retained, added, replaced or removed; the exact proposed equipment configuration; and the customer outcome the change must support. Keep an equipment proposal distinct from an approved target configuration.
Then compare the actual options: reuse the occupied location, use another agreed location within the same facility, or relocate the affected equipment to another facility. Each option needs its own interface and operating constraints. An existing tenancy, an empty cabinet position or a destination reservation does not establish suitability for the proposed equipment. The relevant facility, OEM and design owners must decide that against the actual configuration and current site information.
Ask the customer service owner to state what must remain available during the change and what interruption, if any, may be considered. If that owner has not agreed a service-impact condition, record it as unresolved. Do not convert a desired completion date into an assumed outage allowance, or promise a parallel build before the space, interfaces, equipment and operating approach have been confirmed. The following planning sequence organizes those decisions; it supplies no engineering assessment or cutover procedure.
Build one current-state packet for every retrofit option
Give the people evaluating each option the same identified starting point. Separate the current approved records, dated as-found observations and proposed changes. When a drawing and an observation disagree, preserve both references and the unresolved question; neither should silently overwrite the other. Identify the author and issue of the proposed equipment list, rather than circulate several unlabelled versions as the AI upgrade.
NASA's configuration-management guidance treats an approved current baseline as the basis for a change and retains the status of proposed changes and discrepancies. That general record principle supports a traceable starting point here. This worksheet and its colocation decision roles are original editorial applications, not NASA site-design guidance.
Keep the main brief useful without publishing a detailed operational map. Refer to restricted connection, access and system records through the customer's authorized channels. A coordinator can identify a missing decision, its responsible owner and the source needed to resolve it; collecting the documents does not confer authority to approve their technical contents.
References: [M1]
Scroll the table horizontally on smaller screens.
| Record group | What to identify | Decision it supports | Source |
|---|---|---|---|
| Current and target equipment | Retained/added/replaced/removed item identities; current record issue; proposed exact configuration and its issue. | Customer equipment and design owners establish what change is actually being assessed. | Planning analysis |
| Occupied site and intended location | Current locations, applicable drawings, dated observations, proposed locations and any conflicting or missing record. | Facility and qualified design owners determine whether each option can be supported and what further work or evidence is required. | Planning analysis |
| Connected services and shared interfaces | Affected endpoint/service references, supporting equipment that remains, interface owners and the current issued provider/tenant scope. | The responsible network, facility and service owners identify dependencies that moving the compute equipment alone would leave unresolved. | Planning analysis |
| Equipment and material readiness | Actual equipment-list issue, appointed supplier/delivery owner, required accessories and what is confirmed, unavailable or still awaiting selection. | The customer and appointed suppliers reconcile the inputs before an assembly or move package relies on them; no Leviathan purchasing commitment is implied. | Planning analysis |
| Service impact and working interfaces | Services to retain; customer interruption constraints; access/work-area decisions; affected teams and external dependencies. | Authorized operating and site owners agree the applicable conditions and controls; no shutdown, change-window or parallel-operation permission is inferred. | Planning analysis |
| Result and handoff | Required physical records, receiving/reviewing owners, separately required technical decisions and the treatment of unresolved items. | The customer distinguishes the intended physical result from installation acceptance and permission to return the service to operation. | Planning analysis |
Project-designed information checklist, not a site-survey specification, capacity calculation, engineering approval, procurement offer or security procedure. Applicable specialists determine the actual evidence and decisions.
Compare retrofit options with their unresolved dependencies
In fictional retrofit EX-RT15, an enterprise proposes replacing equipment group EX-A with EX-B. Current-state packet C4 identifies EX-A and its existing service references; target proposal T2 identifies EX-B. The customer has said EX-A must remain available until it authorizes a transition, but has not approved an interruption or a technical transition plan. Those statements are the example's inputs, not evidence that uninterrupted replacement is feasible.
The team compares three alternative locations for the same T2 proposal. It does not present them as three approved work packages or add their apparent benefits together. Option A reuses the occupied area; option B proposes another area in the same facility; option C proposes a different facility. The table records what remains to be decided instead of assigning a readiness score from partial information.
For example, if the responsible owners determine that A requires a service interruption and the customer does not accept that condition, A cannot satisfy the current brief. That does not establish that B or C works. Each still needs its own equipment-specific decisions and confirmed interfaces. A provider's released space or a completed connection order can answer one dependency without approving the whole retrofit.
Record why an option is selected, rejected or awaiting information, with the actual decision owner and referenced issues. If T2 changes to T3, the responsible owners must identify which previous decisions remain applicable. Keep the earlier reasoning; do not silently carry an approval for different equipment or a different location into the new proposal.
Scroll the table horizontally on smaller screens.
| Alternative | Known fictional starting point | Specific unresolved decision | Source |
|---|---|---|---|
| A — Reuse the occupied area | EX-A is in place. No equipment-specific disposition for EX-B or customer-approved interruption is supplied. | Facility/design owners assess the proposed change and affected interfaces; the customer service owner decides whether the resulting operating conditions can meet the brief. | Planning analysis |
| B — Another area in the same facility | The customer has identified a candidate area. No confirmed support for T2, parallel-operation approach or final service endpoints is supplied. | The relevant owners confirm the location and interfaces, dependencies on EX-A and the operating approach before a staged installation is treated as available. | Planning analysis |
| C — Another facility | A possible destination is identified. Equipment suitability, connection boundaries, receiving arrangements and the technical transition remain unconfirmed. | Destination and customer owners resolve those inputs; source-side service and any later removal remain separately controlled even if destination preparation proceeds. | Planning analysis |
Original fictional option comparison. C4 and T2 are document issues, not technical specifications. The table establishes no capacity, compatibility, downtime, cost, availability, staffing or preferred site, and no live work is authorized.
Carry the selected retrofit decision into work and handoff
First, retain the selected option, current-state and target issues, the decisions supporting it and the specific conditions that remain open. A commercial or location preference can be recorded while technical questions are outstanding, but it should not be represented as permission to install. Give each unresolved input a named receiving owner and a clear question, rather than a general confirm readiness action.
Next, have the responsible owners establish the physical and operating interfaces for the selected option: what remains in service, which equipment or connections change, what must be available before a dependent task and who may release each part. Keep customer/provider work and the requested tenant-side package explicit. Confirm the appointed equipment/material supply arrangements and the actual delivery inputs before those inputs appear as available in a work package.
Before physical work relies on the plan, identify the issued records and actual authorizations that release that work. The customer operating owners retain shutdown, service transition, recovery and return-to-service decisions; relevant specialists retain equipment/site design, facility interfaces and verification requirements. If a decision or dependency changes, update the affected package through its responsible owner. This sequence defines responsibility and information flow, not the order in which equipment should be disconnected, moved or energized.
At handoff, explain what changed from the starting point: retained and replacement equipment references, actual locations and endpoints, the applicable work/verification records, unresolved items and the owner of each remaining decision. Keep planned destinations separate from observed installation and technical acceptance. Reusing the same site still requires the change history; it is not a move with zero documentary work. Where a relocation is selected, the source-to-destination crosswalk and manifest/receipt distinctions below become part of that chosen physical package. Retirement of EX-A and service restoration each need their own actual disposition, rather than following automatically from delivery of EX-B.
Reconcile the source inventory before designing the move
Record the equipment identifiers, installed locations and physical connections that the agreed move will affect. Reference the approved drawings and distinguish observed as-found conditions from the intended source configuration. Identify equipment or links that must remain in service, along with the operator responsible for protecting them.
If labels and records conflict, resolve the identity question before an authorized disconnection task depends on it. Do not infer the connection from cable appearance or a familiar neighboring port. A source inventory should also identify the customer owner for data, media and access permissions; do not put passwords or private network details in a broadly shared move sheet.
Release the destination as a separate package
Confirm the purchased equipment and applicable OEM documents against the destination’s approved rack locations, routes, service access and facility interface records. Record the facility and relevant specialist decisions. A similar cabinet or connector is not proof that the destination is suitable.
Check installation authorization and the manufacturer’s relocation requirements. NVIDIA’s DGX B200 guidance demonstrates that installation and system operation have specific requirements. Use the actual system and current instructions, not a generic GPU shutdown or restart sequence from an article.
Separate the AMD platform from the existing rack and fabric
An AMD retrofit should begin with the supplied server, rather than transfer the dimensions or network name of its accelerator platform to the room. AMD lists the MI300X platform as UBB 2.0 with eight MI300X OAMs. Its versioned ROCm 7.2.4 reference-node explanation distinguishes GPU-to-GPU Infinity Fabric from the PCIe connections to the host. That reference depicts an EPYC-based node; it is not the system drawing for every OEM server. [A7, A8]
Dell's July 2025 XE9680 guide supplies a different boundary: a 6U air-cooled complete server, with an eight-MI300X configuration among its listed alternatives. These facts identify the unit to evaluate; they do not establish a purchased configuration or an interchange of accelerator boards. A universal baseboard is not an external rack standard, and its internal GPU interconnect is not an instruction for the existing room's network. [D7]
For the occupied rack, compare the proposed complete-server configuration with the actual released mounting positions, rails and retention package, service access, configured weight, supplied power connections and applicable system demand and cooling requirements. A currently working rack does not answer those changed-equipment questions. The facility and equipment owners need the relevant source editions and the actual proposed configuration; this article supplies no load, thermal or site-fit calculation.
Treat the fabric comparison separately. Identify the supplied host adapters, physical interfaces, intended compute, storage and management roles, and the actual switch and cable assemblies affected. Internal Infinity Fabric does not by itself decide whether an external connection is Ethernet or InfiniBand, or whether an existing adapter, optic, cable or software combination can be retained. Those are configuration-specific returns for the appointed system and network owners. Preserve a genuine no-change decision too: replacing compute does not mean every supporting network must change.
In fictional EX-AR142, a proposal names one XE9680 with eight MI300X GPUs. The current rack record releases five contiguous mounting units for the proposed chassis; another two units are occupied by equipment that has not been released for retirement. The 6U chassis description does not fit within that stated five-unit allowance. Adding the two occupied units to claim seven available units would invent a removal decision. Even a later confirmed six-unit allowance would resolve only this height comparison, leaving the other mechanical and facility questions separate. The network return also says only existing high-speed fabric, without the adapter and endpoint configuration; the AMD platform name cannot fill that missing return.
Scroll the table horizontally on smaller screens.
| Boundary | Fictional input or named source | Result at this boundary | Source |
|---|---|---|---|
| Equipment unit | One proposed complete XE9680; its cited guide describes a 6U system and an eight-MI300X option. | Evaluate the actual OEM server configuration, not bare UBB dimensions. | [D7] |
| Current mounting allowance | Five contiguous units released; two further units occupied and not released. | The six-unit chassis exceeds the stated current allowance by one unit. There is no seven-unit released space. | Planning analysis |
| External fabric | Only a general fabric label is returned; adapter, local/remote interface and cable applicability are absent. | No retain-or-replace interconnect decision is established by the GPU platform name. | Planning analysis |
| Other rack and facility interfaces | No configured weight, rail, access, whole-system demand or applicable site disposition is supplied. | Height arithmetic alone cannot release installation or settle suitability. | Planning analysis |
Original hypothetical inputs and simple 6-versus-5 comparison, not measured rack geometry, structural/electrical/cooling assessment, available hardware, removal permission or an AMD/OEM retrofit method.
Coordinate compute and storage by network role, not delivery label
A compute delivery and a storage delivery can each be described as network-ready while leaving different interfaces unanswered. Separate the compute cluster interconnect, the storage service's client-facing connections, the storage system's own node-to-node network and management. These roles are not interchangeable merely because two products expose similar connectors or use the same broad network technology.
The named NVIDIA DGX H100/H200 guide distinguishes cluster networking, storage and in-band-management cards, and out-of-band BMC management. Its DGX H100 component description also distinguishes local operating-system and data-cache storage from those network interfaces. A local-drive population therefore does not identify a separately supplied shared storage service. [N7]
Dell's OneFS 9.15 networking overview describes PowerScale's internal network for node communication and its external network for client connections. It also makes the external technology model-dependent rather than universally Ethernet. These are the cited system's role distinctions, not a recommendation to attach a DGX server directly to any particular PowerScale port. Exact model, configuration, permitted architecture and supported components remain necessary. [D8]
Ask the compute supplier to return its actual storage-facing interface and the boundary of its delivered package. Ask the storage supplier for the client-facing boundary and its separately required internal-cluster components. Then have the appointed network owner reconcile the two with the issued switching, patching, media, endpoint and responsibility design. Keep the actual equipment/material supplier for each connecting item explicit; one OEM's shipment does not automatically contain the other OEM's interconnect package.
For an existing GPU cluster, first state what storage change is intended: a new storage service, more nodes in an existing supported storage system, or replacement of an old service. Those are different changes. The authorized storage owner must establish how the offered equipment joins the intended service, while the compute owner states which clients and workloads change. An approved physical addition should preserve clearly identified existing compute links that are outside its scope; a larger storage population does not itself authorize a compute-fabric cutover.
Scroll the table horizontally on smaller screens.
| Role | Narrow source example | Buyer coordination consequence | Source |
|---|---|---|---|
| Compute cluster network | DGX H100/H200 separately identifies cluster-network interfaces. | Do not silently use a compute-fabric connection as the storage client return. | [N7] |
| Compute-side storage connection | The same guide separately lists storage and in-band-management cards. | Identify the actual supplied adapter/interface and issued remote connection, rather than infer it from local SSD capacity. | [N7] |
| Storage client boundary | PowerScale OneFS distinguishes the external client network from its internal network. | Obtain the actual model-specific client-facing return and reconcile it with the network design. | [D8] |
| Storage-internal boundary | OneFS separately describes node-to-node communication. | Keep storage-internal components and delivery responsibility distinct from the client-facing patch package. | [D8] |
| Management and operating release | The DGX guide identifies BMC management separately; no actual operating result is supplied here. | Identify the management/operating owners; an arrived storage cabinet is not an authorized usable service. | [N7] |
Source-qualified role comparison only. No compatible vendor pairing, topology, port count, network speed, cable length, supported software, delivered state or connection instruction is established.
Decide what a delayed storage interface actually blocks
Fictional EX-DC143 has one proposed compute package C and one proposed storage package S from different suppliers. Each supplier has identified its delivered equipment, but the customer has not approved the combined system. C's equipment identity and agreed mounting inputs are returned. S's client-facing interface return is still missing. Its storage-internal package has a separate supplier return. No installed or tested connection is claimed by these statements.
Build dependencies around the intended result instead of a single whole-project delivery date. The coordinator can reconcile C's delivered equipment and its proposed mounting package without pretending S's client interface has been resolved. Whether any separate physical work may proceed requires its own actual release and work-area conditions. The dependent client connection cannot be treated as defined while one end remains unknown, and the customer cannot infer an available storage service from C's receipt or mounting.
Compare two variants of the same project. In variant A, C is new compute that will use S. Its storage-dependent application result waits for the complete authorized interface and operating evidence. In variant B, C is an already operating cluster and S is an addition. The client owner must identify which existing connections, if any, are to change. If none are approved to change, their preservation is a scope boundary, not permission to disturb them in anticipation of the new storage. A proposal to reuse an occupied switch port is a change to assess, not free capacity created by S's arrival.
The useful order of decisions is: confirm each delivered unit and intended service; reconcile the client-facing and storage-internal boundaries; resolve material and facility dependencies; release each defined physical package; then obtain the separately required storage, network and workload results from their actual owners. Earlier stages can produce real documentary outputs while a later stage remains unresolved. This is a decision sequence, not the order in which to disconnect, patch, power, configure or test equipment.
If the design calls for repatching, retain the approved before and intended after endpoints, affected service, configuration issues, allowed interruption and named decision owner. A return plan also needs the actual state in which reversal remains valid and the authorized recovery procedure. Reversing an endpoint list does not restore an earlier software, storage or workload state. The physical patch order, checks, rollback triggers and operating recovery for the actual system are not supplied by this example; they must be resolved before that work relies on the plan.
Scroll the table horizontally on smaller screens.
| Statement | Fictional evidence | Decision that remains | Source |
|---|---|---|---|
| Compute equipment package identified | C has an equipment identity and mounting-input return. | The responsible owner still releases any actual work. This does not complete S or its client connection. | Planning analysis |
| Storage-internal package described | S has a supplier return for its internal-cluster package. | Its separate missing client-facing return is still required; the two packages are not interchangeable. | Planning analysis |
| Storage-dependent result requested | Variant A needs new compute to use S; variant B adds S to existing compute. | Appointed owners define the affected clients, approved connection changes and required operating evidence. Neither variant has a service result yet. | Planning analysis |
Original fictional dependency comparison; no supplier date, labor allocation, site release, available spare port, software operation, patch/cutover/rollback method or customer acceptance is asserted.
Create a source-to-destination crosswalk
Keep stable equipment and cable identifiers where the approved design permits them. If an identifier changes, preserve the old-to-new relationship. The crosswalk should let the receiving team trace what moved, what changed and which approved record authorized the change.
Use a controlled record with separate columns for intended destination and verified final location. Protect sensitive site and connection information according to the customer’s access rules.
Scroll the table horizontally on smaller screens.
| Record | Source-side information | Destination-side information | Source |
|---|---|---|---|
| Equipment | Asset ID, accessible serial and current cabinet/position | Approved destination and observed installed position | Planning analysis |
| Connection | Cable ID and documented source endpoints | Approved new endpoints; retained or changed identifier | Planning analysis |
| Condition | As-found observation and evidence reference | Post-move observation and issue reference | Planning analysis |
| Movement | Approved handling-package reference and custody handoff | Receiving acknowledgement and permitted staging location | Planning analysis |
| Release | Authorized source work-package disposition | Destination installation and separate technical release owners | Planning analysis |
Original planning worksheet. Agree the fields and responsibilities for the project; this is not a safety procedure or acceptance standard.
Keep the approved manifest, receipt and installed record distinct
A move record needs to answer three different questions: what was approved to move, what the receiving party observed and where the equipment was actually installed. Keep those views related without copying one into the others as if the proposed destination had already been achieved. A package reference links items for a particular transfer; it does not replace the individual equipment identifiers.
Start with the released move-manifest revision and the asset identifiers it contains. Link each applicable receipt to that revision, its package reference, the observed item identifiers and any exception. Record the final installed position only when it has its own evidence. Equipment can be received into agreed staging while its intended rack position remains pending. Keep that distinction visible instead of using a single complete checkbox.
NASA’s configuration-management guidance separates item identification, approved baselines, change status and discrepancy history. The following original worksheets apply those general record principles to a fictional equipment move. They are not a NASA migration procedure. Agree the actual fields, access controls and decision owners for the engagement.
References: [M1]
Reconcile asset identities instead of matching only package totals
In fictional move EX-MV-19, released manifest R2 contains four assets. Package PK-A is expected to contain servers S-11 and S-12; PK-B is expected to contain switch SW-11 and server S-13. The receiving record reports that both packages arrived, with four items in total. However, its observed identifiers are S-11, S-12, SW-99 and S-13. The expected SW-11 is not evidenced by that receipt, and SW-99 has no matching line in R2. Four received items therefore do not establish that all four expected assets arrived.
The coordinator preserves the observed identifier and opens a specific reconciliation question. The asset owner must establish whether the discrepancy is a recording error, an approved substitution or a different item before the record is reconciled. The example does not infer loss, damage, ownership or an authorized substitute. Correct the record through its history when the actual evidence supports a decision; do not silently change SW-99 into SW-11 to make the totals agree.
Scroll the table horizontally on smaller screens.
| Manifest R2 expectation | Receipt observation | Documentary disposition | Source |
|---|---|---|---|
| S-11 in PK-A | S-11 observed in PK-A | Identity matches the expected line; installation and technical release remain separate. | Planning analysis |
| S-12 in PK-A | S-12 observed in PK-A | Identity matches the expected line; an agreed staging location is not a final installed position. | Planning analysis |
| SW-11 in PK-B | No SW-11 identity evidenced in the receipt | One expected asset remains unmatched; asset owner resolves the specific evidence question. | Planning analysis |
| S-13 in PK-B | S-13 observed in PK-B | Identity matches the expected line; any agreed condition observations remain with the receipt. | Planning analysis |
| No R2 line for SW-99 | SW-99 observed in PK-B | One observed item remains unmatched; retain its actual reference and request an authorized disposition. | Planning analysis |
Original fictional inventory example: four expected assets and four observed items, with three identity matches, one unmatched expectation and one unmatched observed item. These counts do not establish condition, delivery acceptance, title, transport compliance or operational readiness.
Show where the physical package stops before return to service
Continue EX-MV-19 without inventing a successful outcome. The record can show two package arrivals and three matched asset identities while the SW-11/SW-99 question is still unresolved. Those are different statements with different denominators. Report the missing decision rather than turn the package count into an asset-reconciliation or service-restoration percentage.
For a matched item, keep its observed destination distinct from its approved destination. If S-12 has reached agreed staging but not its intended rack position, say so. If the customer later assigns a new destination identifier, link the old and new references to the actual item and the authorized change. Similar model names or appearance alone do not resolve an identity conflict.
The closing package can then state which assets have reconciled identity/location records, which installation evidence is available and which exceptions remain with named owners. Physical receipt, agreed installation completion and customer/OEM return-to-service decisions must remain identifiable separately. Leviathan’s relocation service describes destination reconciliation and an exception/closure list within an agreed engagement; the actual logistics, specialist resources and surrounding system responsibilities are confirmed for that engagement.
References: [L6]
Scroll the table horizontally on smaller screens.
| Record view | What the fictional snapshot supports | What it does not establish | Source |
|---|---|---|---|
| Package arrivals | PK-A and PK-B are recorded as arrived. | That every expected asset or separately listed accessory is reconciled. | Planning analysis |
| Asset identity comparison | Three expected identities match; SW-11 and SW-99 require a disposition. | A conclusion about loss, damage, a permitted substitution or a successful whole move. | Planning analysis |
| Location evidence for S-12 | Received into the agreed staging location; intended installed position remains pending. | That the intended rack position is already an as-installed fact. | Planning analysis |
| Technical and service release | No result is supplied by this documentary example. | Installation acceptance, OEM health/test approval or authority to restart workloads. | Planning analysis |
Original fictional status comparison, not a transport instruction, contract term, claim deadline, inspection method or completed project. Report actual evidence and separately authorized decisions for the real equipment.
Define independent holds and a return decision
Separate the authorization to stop service, disconnect equipment, move it, install it and return it to operation. Each depends on the relevant project and facility procedures. Do not treat an installer’s physical completion as permission to energize equipment or restart workloads. Liquid disconnection/reconnection, electrical work and heavy handling need their own confirmed scope and authority.
Before the window, ask the customer and technical owners what conditions cause the affected package to pause, and who can choose an alternate plan. A return or recovery decision must consider the actual system state and relevant approved procedures; this guide supplies no universal rollback sequence.
Close the move with records that explain the differences
Illustrative example: a source server in cabinet A04 is assigned to B09, but the destination design later moves its network connection to another panel. Preserve the asset crosswalk and reference the design change in the endpoint record. Track the affected cable and its agreed verification separately, rather than marking the entire move complete because the server is mounted.
Handoff should identify final locations, revised endpoint records, agreed verification evidence and unresolved items with owners. Leviathan can discuss the separately agreed tenant-side physical installation and documentation package. Freight, storage, specialist rigging, data migration, liquid-side work and system commissioning should not be assumed to be included.
References: [L2]
Common planning questions
Does this guide provide a safe shutdown and cooling-disconnection sequence?
No. Those procedures must come from the actual OEM, facility and authorized technical owners for the equipment and site.
Should existing cables automatically be reused?
No. The design owner must confirm suitability, condition, identifiers and any required verification for the intended destination. Record the decision and affected links.
Do matching shipment and receipt totals prove that the correct equipment arrived?
No. Reconcile the expected item identifiers against the actual observations. In the fictional example, four expected assets and four observed items produce only three identity matches because one expected identifier is missing and one observed identifier is unmatched. Preserve both exceptions until the responsible owner resolves them.
Can equipment in destination staging be marked installed at its planned rack position?
No. Keep the observed staging location separate from the intended installed position. Record installation only when its own evidence is available; receipt, installation completion and return-to-service decisions describe different results.
What happens if the receiving team records a different asset identifier?
Retain the observed identifier and link the discrepancy to the released manifest and package. The authorized asset owner must establish whether the evidence supports a correction, approved substitution or a different disposition. Do not overwrite the observation or assume that matching model names prove identity.
How should we compare retrofitting the existing location with moving to another site?
Use one identified target-equipment proposal and one current-state packet for every option. Compare each location's unresolved equipment/site decisions, affected services, provider/tenant interfaces, material inputs and handoff responsibilities. Record the actual owner decisions and assumptions; an empty position, existing tenancy or reservation does not establish suitability or make another option ready.
Can we assume a same-site retrofit avoids downtime?
No. The customer operating owner must establish the service-impact conditions and the authorized technical approach for the actual change. Keeping equipment in the same facility does not settle shared-interface or interruption dependencies. An unknown interruption requirement stays unresolved rather than being recorded as zero.
What if the target equipment changes after a retrofit option is selected?
Retain the earlier proposal and decision history, issue the changed target clearly and ask the responsible owners which decisions are affected. A disposition for an earlier configuration or location is not automatically applicable to the new one. Update dependent work packages before they rely on the changed inputs.
Does receiving the replacement equipment authorize removal of the existing system?
No. Receipt, physical installation, technical acceptance, service transition and retirement of the existing system are separate results and decisions. The responsible customer, site and technical owners must provide their actual dispositions; this article supplies no shutdown, disconnection, disposal or recovery procedure.
Does an eight-GPU AMD platform establish that a server fits an existing rack and fabric?
No. The platform, complete OEM server and external rack/network interfaces are different boundaries. The worked example compares a named 6U server with a fictional five-unit released allowance and separately missing adapter/endpoint evidence. It demonstrates an unresolved retrofit decision, not a universal site-fit rule or a supported hardware swap.
Can a storage system internal network be treated as the compute client connection?
Not from those labels. The cited OneFS overview distinguishes internal node communication and external client connections. Reconcile the actual storage model, compute-side interface and issued network design; similar connectors or technology names do not establish a compatible pairing or connection method.
What changes when storage is added to an already operating GPU cluster?
Identify the new service and its client-facing and internal-cluster packages, then identify which existing compute connections are actually approved to change. Keep unaffected live connections outside the new physical scope. Storage receipt or a supplier internal-network return does not settle the client connection, operating result or authority to change an occupied port.
Is reversing the physical patch list a complete rollback plan?
No. The actual permitted reversal depends on the current equipment, network, storage and workload state and the authorized recovery procedure. Before/after endpoint records help define the change, but do not supply its physical order, checks, rollback triggers or operating recovery. Those substantive method inputs remain unresolved here.
Primary sources
- [N1] NVIDIA DGX B200 User Guide: installation and basic operationChecked 2026-10-14. DGX B200 only; installation authorization and software/health workflows, not a generic procedure for other systems.
- [L2] Leviathan colocation installation scopeChecked 2026-10-14. Tenant-side physical installation; facility services and authorization remain with the operator.
- [M1] NASA Systems Engineering Handbook, section 6.5: Configuration ManagementChecked 2026-10-19. General unique-identification, controlled baseline/change, current/historical documentation and discrepancy-disposition principles only. The examples and worksheets are original editorial applications, not NASA data-center procedures, standards or endorsement. No technical-method or engineering authority inferred.
- [L6] Leviathan equipment relocation scopeChecked 2026-10-19. Current published origin/destination, receiving reconciliation and exception/closure scope. Logistics, specialist resources, site permissions and technical/system releases remain engagement-specific; no actual move result or availability is asserted.
- [A7] AMD Instinct MI300X Platform: product basicsChecked 2026-10-19. UBB 2.0/eight MI300X OAM identity only; no platform geometry, performance, price, eligibility or complete-server/site applicability adopted.
- [A8] AMD ROCm 7.2.4: MI300 node-level architectureChecked 2026-10-19. Versioned EPYC reference-node distinction between internal GPU Infinity Fabric and host PCIe links only. It is not the Intel-based Dell system drawing or its external network design. No topology, link count/rate or procedure transferred.
- [D7] Dell PowerEdge XE9680 Technical Guide, July 2025 Rev. A09: System overview, page 5Checked 2026-10-19. Existing programme exact saved PDF/page 5 rendered image re-read for 6U air-cooled server and separately listed eight-MI300X option only. Fresh normal web open failed; no new raw download or current orderability claim. No weight/power/rail/site/thermal/method approval.
- [N7] NVIDIA DGX H100/H200 User Guide: component and network-role descriptionsChecked 2026-10-19. Only separate cluster, storage/in-band management, BMC and local OS/cache roles. No quantities, network speeds, operating commands, performance or compatible cross-OEM pairing is adopted.
- [D8] Dell PowerScale OneFS 9.15 Web Administration Guide: networking overviewChecked 2026-10-19. Internal node communication versus external client network and model-dependent external technology only. No protocols/rates/configuration operations, universal topology, live changes, security guarantees or selected system compatibility inferred.