LEVIATHAN SYSTEMS

Liquid Cooling_

Thermal Design Updates During a GPU Refresh: Air and Liquid Interfaces

·Technical content·

Identify how a GPU refresh changes heat paths, equipment populations, facility and technology cooling interfaces, and the evidence needed for a qualified thermal-design update.

Key facts

  • A refresh can change the supplied equipment and its heat-transfer boundaries. Replacing an air-cooled system with a factory liquid-cooled system is different from modifying an existing server; a product comparison establishes no conversion procedure.
  • NVIDIA’s DGX H100/H200 guide documents front-to-back airflow. Its DGX GB rack guide describes liquid-cooled CPU and GPU cold plates while networking and storage components in the compute tray remain air cooled. Liquid cooling does not automatically remove the air-side requirement. [N1, N2]
  • Facility water and the technology cooling circuit are distinct boundaries in Lenovo’s reference discussion. A temperature, fluid requirement or flow figure needs its applicable boundary and configuration. [L1]
  • ASHRAE distinguishes a power-supply nameplate rating from actual equipment heat release and calls for configuration-specific information. Adding PSU ratings is not a thermal-load assessment. [A1]
  • The design update must resolve the selected configuration’s air-side and liquid-side requirements together, with the applicable facility and specialist owners. No universal clearance, coolant recipe, retrofit duration or energy saving is supplied by this article.

Define the equipment change before calling it a cooling retrofit

Start with what is actually changing: adding equipment to the existing air-cooled population, replacing complete systems with a different cooling configuration, or asking an OEM whether a particular modification is supported. These are different proposals. A GPU generation does not identify the enclosure, heat-transfer arrangement or supported service operation. The selected OEM must identify the actual supplied product and applicable documentation; this article gives no cold-plate installation or server-conversion procedure.

NVIDIA’s DGX H100/H200 user guide documents front-to-back airflow for that named system. Its separate DGX GB rack guide describes CPU and GPU cold plates and liquid manifolds, while other compute-tray components still use air cooling. These documents demonstrate a change in thermal interfaces between named products; they are not an instruction to convert an H100 server into a DGX GB tray or a claim that the two products have interchangeable site requirements. [N1, N2]

The first design-update decision is therefore the applicable equipment population and delivery state. Keep the current installed configuration, proposed selected configuration and future option distinct. A reference architecture can explain a cooling approach while the actual supplier package is still missing. It cannot release modifications to the installed equipment.

Update the air-side and liquid-side load boundaries together

For the named DGX GB compute tray, NVIDIA describes liquid cooling at the CPUs and GPUs and air cooling for components such as networking and storage. Moving processor heat to liquid therefore does not establish that room airflow can be removed. The refreshed population may also include separate switches, storage and power equipment that need their own applicable requirements. Do not apply one tray’s cooling description to every item in a rack or hall. [N2]

Request the selected configuration’s heat-release information with its operating assumptions and division between relevant heat paths. ASHRAE’s Handbook explains that a PSU nameplate rating is not actual equipment power draw and is not a basis for computing heat release. Its planning discussion instead points to configuration- and use-specific manufacturer information. A sum of GPU board limits likewise does not describe all equipment in the proposed delivery. [A1]

The appointed thermal owner can then assess the retained air-cooled population, the added or changed liquid-cooled equipment, and the facility’s corresponding heat-rejection arrangements. The result may involve changes to more than one system. A liquid connection being present does not settle residual room cooling, and an existing air-side capacity statement does not establish the capacity of a new liquid circuit. This is a request for a coordinated design assessment, not a load calculation or permission to alter cooling equipment.

Read temperatures and fluids at the boundary they describe

Lenovo’s Neptune reference discussion separates the Facility Water System, or FWS, from the Technology Cooling System, or TCS. In its separated-loop arrangement, the facility liquid stays apart from the technology liquid. ASHRAE’s 2023 Handbook describes a heat exchanger called a cooling distribution unit (CDU): the TCS carries heat from the IT equipment to the exchanger, where it passes to the facility circuit. The two circuits exchange heat without becoming one fluid boundary. [A1, L1]

Transferring heat across that exchanger involves a temperature difference between the fluid streams. ASHRAE calls for the facility owner or designer to account for the planned CDU’s approach temperature when ensuring the proper temperature for the IT equipment. This concerns the temperature relationship across the exchanger; a single loop’s supply-to-return temperature rise instead describes its change as it carries heat. The two comparisons are different, and neither supplies a universal offset to copy into an equipment requirement. [A1]

For an existing refresh, the old facility-water supply entry answers only the facility-side question. The new equipment-side requirement still needs to be reconciled with that condition through the actual intervening CDU arrangement. Ask the appointed thermal and facility owners to return that comparison for the selected configuration. Keeping the old facility condition does not, by itself, establish an acceptable IT inlet. Lenovo’s reference examples describe its own solution scopes rather than universal designs for other OEM equipment. [A1, L1]

Preserve whether each value describes a supply, return, allowable envelope, reference example or control setting, together with its boundary and source revision. ASHRAE also identifies configuration-specific flow and pressure-differential requirements; a class label alone does not complete the comparison. Fluid chemistry, wetted materials and cleanliness likewise need the actual equipment requirements and the responsible specialist’s disposition. This discussion prescribes no fluid selection, dosing, flushing, pressure testing, venting or operating setpoint. [A1]

Work a heat-path comparison without treating it as a site design

EX-TU146 is a fictional buyer comparison using a clearly identified published reference. Lenovo’s LP2018 SR780a V3 H200 solution example states 9.5 kW per chassis, divided into 7.1 kW to water and 2.4 kW to air. [L1]

Suppose a buyer compares two stipulated copies of that chassis population. The source-based arithmetic is 19 kW in total, comprising 14.2 kW to water and 4.8 kW to air. The two heat-path figures are parts of the 19 kW total; adding all three would double count the chassis contribution.

The customer’s old planning sheet has only a total air-side equipment entry. The supplier’s new attachment is the Lenovo reference, while the actual supplied configuration’s thermal return has not arrived. Three decisions follow. The equipment owner must return the actual proposed population and applicable manufacturer requirements. The thermal owner must assess the air and liquid contributions and the corresponding facility interfaces together. The planning owner must keep the old installed basis and proposed refresh basis separately identified until the applicable update is released.

The useful result is the unresolved division of responsibility: “19 kW of cooling exists somewhere” does not identify which system can serve each heat path. The arithmetic covers only two stipulated chassis, excluding the reference’s complete-rack arrangement, other equipment, cooling auxiliaries and facility loads. It represents no measured outcome, purchased BOM, rack-fit finding or completed site assessment, and establishes neither available heat removal nor a feasible retrofit. CDU sizing, flow and acceptable operating conditions remain with the actual configuration-specific design assessment.

Plan the transition around dependencies rather than invented durations

A useful refresh plan identifies which services and equipment remain in operation, which proposed tasks affect their dependencies, and which approved design and readiness returns each task requires. Keep facility cooling work, physical IT installation and the operational return of workloads as separate responsibilities that must be coordinated. A replacement system, a change to a shared cooling circuit and an isolated IT task can have different affected boundaries.

Ask the appointed facility and operational owners to resolve the effect on retained equipment during each proposed phase. Their decision needs the actual plant and distribution arrangement, equipment requirements, affected services and authorized work plan. The word ‘phased’ does not prove that neighboring racks can remain operational, that temporary containment is acceptable, or that a rollback is technically possible. Identify those as decisions to return, rather than supplying an assumed row order or a fixed maintenance window.

If the selected equipment or interface changes, reopen the affected assessment explicitly. Preserve the last applicable release for unaffected work and identify what is awaiting revision. The project must obtain a qualified, applicable plan and an operational decision before work is released; task durations and recovery provisions depend on that plan.

Specify the design-update output and its limits

A complete return should identify the assessed equipment configuration and revision; the air and liquid requirements and their boundaries; affected facility systems and drawings; relevant operating and service conditions; unresolved interfaces; and the appointed design and acceptance owners. Keep a reference calculation, an approved design, a work release and a completed test record separately identified. A supplier’s product document alone is none of the other three.

Have the responsible specialists specify the actual verification and acceptance basis for their systems, including the applicable configuration, conditions, methods, criteria and responsible parties. This article provides no electrical, liquid-side, structural, fire-protection or thermal commissioning procedure. The scope of a physical IT handoff must state which external readiness returns it relied on, rather than implying that documenting the installation certified those systems.

A business case needs its own boundaries too: actual capital scope, IT and cooling energy assumptions, operating period and applicable costs. Do not derive a universal saving or payback period from the cooling label. The source-based heat-path arithmetic above is not an energy measurement, an electricity bill or a retrofit quotation. Leviathan’s separately agreed physical IT work does not include cooling-system selection, rack-power audits, liquid-side or facility electrical work, or full system and software commissioning.

For the surrounding physical IT installation, use the linked rack-and-stack service and project inquiry to discuss separately agreed scope. Share the selected configuration, current and released equipment positions and drawings, and the appointed specialists’ readiness and interface returns. Identify what remains open so the installation discussion can use the applicable physical package without taking over cooling design or acceptance.

Frequently asked_

Does liquid cooling remove the need for room air cooling?

Not automatically. The named DGX GB compute-tray description retains air cooling for networking and storage components alongside liquid-cooled CPUs and GPUs. Assess the actual selected equipment and the retained air-cooled population; do not assume a universal heat-capture percentage. [N2]

Can the existing water-temperature setting be reused for the refreshed equipment?

That requires the applicable OEM and specialist assessment. Identify the facility and technology-loop boundaries, actual configuration and document revision, and distinguish requirements from a reference example or control setting. A class label or another system’s setpoint is insufficient. [A1, L1]

Does a GPU cooling refresh always require an electrical upgrade?

The selected equipment’s actual power and facility requirements must be assessed against the applicable site design. A change in cooling approach alone does not establish an electrical demand or a required upgrade. Board ratings, PSU nameplates and the fictional heat-path comparison are not complete facility-design inputs. [A1]

Does Leviathan perform the cooling conversion and thermal commissioning?

No. Leviathan’s offered work is separately agreed physical IT installation, cabling, inspection, remediation and documentation. Cooling-system selection, rack-power audits, liquid-side work and facility electrical work are outside that offer, as is full system or software commissioning. The customer assigns those responsibilities and acceptance to the appropriate OEM and qualified specialists.

Discuss Your Infrastructure Project_

Tell us about your project, and our team will follow up to discuss the scope, requirements and availability.

Discuss a ProjectEmail Project Scope