LEVIATHAN SYSTEMS

Testing

GPU Cluster Acceptance Test Plan: Scope, Evidence and Sign-Off

Technical contentPublished Updated

An acceptance test plan states what evidence will establish each agreed requirement, under which method and criteria, and who can accept the result. Keep physical installation evidence separate from facility, optical, network, software and application acceptance instead of asking one signature to certify the whole cluster.

Connect scope, requirement and evidence

Start with the agreed work package and the buyer’s acceptance decision. Give each acceptance item an identifier and reference the requirement it must satisfy. State the equipment, link or document that the item covers. Do not add a cooling, electrical or software procedure simply because the overall project is called a GPU cluster deployment.

The SOW and ATP serve related but distinct purposes. The SOW establishes what has been agreed; the ATP makes the verification and acceptance evidence explicit. If the plan reveals a missing activity, resolve its scope and ownership through the project’s agreed process before promising that result.

Define the method before assigning pass or fail

For each technical measurement, the responsible specialist must define the applicable configuration, method, reference setup, instruments, criteria and report format. Confirm the actual personnel and equipment availability. A general requirement to test everything is not enough to determine an acceptable result.

Fluke distinguishes OLTS insertion-loss measurement from OTDR characterization. This is why a continuity observation or an instrument name cannot substitute for a defined optical test package. This article sets no loss budget, wavelength, pressure, voltage, torque, timing or workload threshold.

References: [F1][L5]

Compare a zero-finding return with its finite-lot model

Two QA offers can both report zero findings while checking different numbers of identified records. That return does not identify how many discrepancies remain in the complete lot. NIST distinguishes the lot-disposition purpose of acceptance sampling from estimating lot quality. The narrower question here is how often a stated random model would return zero findings when its lot already contains a stipulated number of discrepancies.

EX-LOT-20 contains twenty fixed fictional rack-document packages, EX-P01 through EX-P20. Exactly two lack a required documentary reference; the other eighteen contain it. This is one stipulated, non-safety documentary criterion, with perfect recognition of the missing reference assumed. It supplies no design, condition or hardware finding. The complete-lot count D = 2 is given by the example, not inferred from checking a subset.

Compare alternative subsets of five and ten packages. In each alternative, every subset of the stated size is equally likely, and no package can appear twice within a subset: selection is without replacement. Count the event of zero discrepancies, denoted X = 0. This numerical comparison does not recommend a real acceptance rule or sample size.

Let C(a, b) count the ways to choose b distinct items from a items without regard to order. A size-n subset can be any of C(20, n) equally likely combinations. To contain neither discrepant package, all n must come from the eighteen other packages, giving C(18, n) combinations. Therefore P(X = 0 | N = 20, D = 2, n) = C(18, n) / C(20, n). The table gives the exact finite counts. The handbook's binomial treatment assumes a lot very large relative to its sample; that approximation is not used for this twenty-package case.

Both rows have a positive chance of returning zero even though the stipulated lot contains two discrepancies. For n = 5 that chance is about 55.263%; for n = 10 it is about 23.684%. These are forward probabilities of zero findings under the given model. They are not probabilities that an actual zero-find lot is discrepancy-free, percentages of good equipment, confidence levels or estimates of an unknown discrepancy count. The comparison alone does not establish which offer meets the buyer's requirement.

Before relying on such a numerical claim, establish the actual defined population, criterion, selection basis and stated decision rule. A first-build, convenience or accessible-only subset does not satisfy this uniform-subset model. Changing identities, rework, mixed criteria or imperfect classification also require their own supported treatment; the invented probabilities cannot fill those gaps.

Any company, contract, OEM or site requirement for complete checking remains binding. Nothing here waives a required 100% check, outage authorization, safety prerequisite or qualified review, or selects an AQL, risk target, inspection method or physical disposition. The actual ATP and appointed authorities still determine the required evidence and acceptance decision.

References: [NS1][NS2][NS3]

Scroll the table horizontally on smaller screens.

EX-LOT-20: zero-finding counts for the same stipulated twenty-package lot
Fictional sample size nAll equally likely subsets C(20, n)Zero-finding subsets C(18, n)Conditional P(X = 0 | D = 2)Source
515,5048,56821/38 ≈ 55.263%Planning analysis
10184,75643,7589/38 ≈ 23.684%Planning analysis

Original fictional subset-counting example: N = 20, D = 2, one non-safety criterion, perfect classification and uniform selection without replacement. The two rows are alternatives, not inspections performed. Percentages are rounded; no plan, confidence level, physical acceptance or release is prescribed.

Use a matrix that preserves the responsibility boundaries

The matrix is an original example of record structure, not a complete project ATP. Replace each illustrative item with the actual approved requirement and assign the authorized reviewer. Keep not-in-scope and not-yet-verified separate from pass.

Scroll the table horizontally on smaller screens.

Illustrative physical acceptance matrix
ItemEvidence to defineAccepting owner to nameSource
Equipment locationAsset and position record against approved elevationCustomer asset/design ownerPlanning analysis
Cable identificationEndpoint record and label verification against released scheduleCustomer network/physical design ownerPlanning analysis
Visible physical workAgreed inspection observations and exceptionsAuthorized physical inspection reviewerPlanning analysis
Formal optical measurement, if scopedSpecialist-approved method, criteria and reportConfirmed test/technical reviewerPlanning analysis
Facility/OEM readinessSeparate discipline-specific release recordAuthorized facility/OEM ownerPlanning analysis
Software or workload resultSeparate approved technical acceptance planNetwork, systems or application ownerPlanning analysis

Original planning worksheet. Agree the fields and responsibilities for the project; this is not a safety procedure or acceptance standard.

Give each commissioning hold point a release decision

A commissioning hold point connects a named next activity to an explicit release decision. The contractor supplies the defined readiness or result evidence; the appointed reviewer decides whether that evidence satisfies the agreed condition; the person with the project authority releases the next activity. Those roles may belong to different people. A scheduled test, a completed installation checklist and permission to proceed are not interchangeable. Define the affected system, prerequisites, reviewer, release authority and consequence of an unresolved item before the team reaches the gate.

A concrete published example appears in UFGS 23 08 00, the federal guide specification for commissioning mechanical and plumbing systems. Its Certificate of Readiness provisions link specified prerequisite records and signatures to government approval before the associated functional performance tests are scheduled. That is an example of a documented prerequisite-and-release relationship in its stated federal mechanical scope, not an adopted GPU-cluster procedure or a grant of authority to a contractor or customer here. [U1]

The DOE commissioning guide likewise separates preparation and contractor review of test procedures from witnessed functional testing and later deficiency resolution. Use that distinction when agreeing who prepares the package, who reviews technical adequacy, who must attend and who can release the next stage. A witness invitation or a signature acknowledging receipt does not, by itself, establish that a different required release decision has been made. The actual plan must specify any notice, attendance, substitution or deferral arrangements. [D1]

In fictional EX-HP152, the parties have already stipulated the three documentary gates below. At G1 the procedure revision is present but the required configuration reference is absent, so the stated readiness condition remains unmet. A witness attending G2 cannot repair that earlier missing decision, and a G2 result cannot by itself close G3. The example teaches the dependency between decisions; it supplies no test procedure, technical pass limit or actual permission to start work.

References: [U1][D1]

Scroll the table horizontally on smaller screens.

EX-HP152: three stipulated gates answer three different questions
Gate and next activityEvidence and roles stipulated in the exampleWhat the return establishesSource
G1: release the named test sessionThe contractor submits procedure P4 and configuration reference C2; the appointed technical reviewer checks both, and the named release authority records the decision.P4 is returned without C2. The stipulated readiness condition is incomplete; there is no recorded G1 release.Planning analysis
G2: close the witnessed test eventThe agreed test record must identify its actual item, configuration, result and required witness observation, using the approved technical procedure.Attendance alone is not a test result, technical acceptance or a replacement for the missing G1 decision.Planning analysis
G3: release the defined handoff packageThe recipient reviews the required result population and open items; the authorized accepting party makes the bounded handoff decision.A received report does not automatically resolve exceptions or accept other systems. Any deferral needs its own actual authorized disposition.Planning analysis

Original fictional decision sequence. The actual project defines its gates, authority, witnessing conditions, technical prerequisites and permitted next activities. No real system or activity is released.

Treat an exception as a decision, not an erased result

An exception record should identify the item, observed result, affected requirement, owner and disposition. Preserve original evidence and any later correction or retest history. A deferred item needs the authorized customer decision and its stated limits; a blank cell is not acceptance.

Illustrative example: a cable is physically installed and carries the intended identifier, but its formal report is missing. Record the installation observation as its own evidence and keep the report-dependent acceptance item unresolved. Do not infer certification from the installed cable or ask a different reviewer to sign without the required evidence.

Keep factory acceptance inside its tested boundary

For a modular data center, distinguish acceptance of the defined factory test package from acceptance of the installed site arrangement. A factory acceptance test, or FAT, concerns the supplied unit and the configuration, interfaces and conditions actually included in that factory plan. A site acceptance test, or SAT, concerns the agreed installed arrangement and site conditions in its own plan. The acronyms do not establish a universal checklist, test method or contractual meaning; read the actual scope behind each one.

Schneider Electric describes its prefabricated modular IT pod as preconfigured and factory-tested, then transported partially assembled; it also describes a prefabricated data hall as factory-built modules joined on site. Those are concrete product-boundary examples, not evidence that a particular delivery has passed an agreed FAT or that its site connections have been accepted. The DOE guide explicitly treats review of factory acceptance tests as an input to deciding what further testing is needed against the specifications. [S1, D1]

Compare the named unit and revision, included interfaces, test environment, unresolved exceptions and subsequent changes. A report for an internal factory connection may be relevant evidence for that connection without covering a later connection between modules or to the facility. Conversely, do not discard a matching factory report merely because it was produced elsewhere: the appointed reviewer decides its applicability and what additional site evidence is required. Transport condition, substitutions or rework can create questions about that applicability; this article makes no automatic pass, failure or mandatory-retest decision.

Fictional EX-FS152 contains two factory reports, F-A for module M-A and F-B for M-B. The example stipulates that each report covers only the named module's internal connection set. The site plan separately names I-AB between the modules and I-S between the delivered arrangement and the site. Two factory reports therefore supply evidence for two internal sets and, on the stipulated scope, zero of those two site interfaces. This is coverage arithmetic for the example, not a finding about installed modules or a complete modular-data-center test programme.

References: [S1][D1]

Scroll the table horizontally on smaller screens.

EX-FS152: preserve useful factory evidence without extending its scope
Object or interfaceEvidence supplied in the exampleSite acceptance conclusion still openSource
Internal connection set of M-AF-A identifies M-A and its factory-tested configuration.Whether that configuration and report remain applicable to the delivered arrangement, including any relevant change or exception.Planning analysis
Internal connection set of M-BF-B identifies M-B and its factory-tested configuration.The same applicability decision for M-B; F-A is not evidence for a different module.Planning analysis
I-AB: connection between M-A and M-BNeither factory report includes this separately named site interface.The site plan's required interface evidence and the appointed technical review remain outstanding.Planning analysis
I-S: connection from the delivered arrangement to the siteNeither factory report includes this separately named site interface.The actual facility/interface scope, required evidence and authorized site decision remain outstanding.Planning analysis

Two factory reports, two named internal sets and two separately scoped site interfaces. Zero site-interface conclusions are established by those reports alone. No energization, functional test, compatibility, operational readiness or customer acceptance is claimed.

Issue the physical handoff without overclaiming

Agree the deliverable format, reviewer access, document revision and treatment of open items before execution. Link each acceptance record to its equipment or connection identifier. Keep separate facility or software packages visible so the recipient understands what the physical handoff establishes and what remains with other teams.

Leviathan can scope visual inspection, identification, label verification, physical connectivity checks, defect recording and agreed handoff documentation. OTDR, OLTS, copper certification or other formal procedures require confirmation of the specific equipment, personnel, method and acceptance criteria. No full-system commissioning or universal test capability is implied.

References: [L5]

Use the example acceptance evidence index

Use the example acceptance evidence index linked under Related Leviathan resources to identify the evidence or decision still owed for a named gate. The package contains five CSV schemas, populated fictional inputs, a Python checker, adverse fixtures and expected outputs. All names, references and states are invented; no reports or performed results are supplied.

One requirement row binds a stable requirement ID to an item, configuration, revision, gate, evidence slot and next owner. The evidence register describes each offered record’s scope separately. A shared evidence ID can therefore match one requirement and fail to cover another. The gate register identifies the prerequisite gate and decision owner; the returned exceptions.csv separately labels each exception’s affected requirement, exception_next_owner and disposition_ref. requirements.csv labels requirement_next_owner; gates.csv keeps decision_owner and decision_ref. report.json retains the same separate records.

In the baseline, R-C2 requires configuration evidence C2, which is absent. W2 is an attendance reference for a different slot: it cannot fill C2, so G1 remains PENDING. G3 requires handoff disposition D3; report receipt RCPT3 cannot supply it. These returns identify the missing records without interpreting a technical result.

The site-interface rows deliberately offer F-A and F-B as candidate evidence. Their internal-module item, configuration and scope do not match I-AB or I-S. The checker leaves R-IAB and R-IS UNKNOWN while preserving the two internal-module entries for their own pending review. Q-IS keeps the unresolved exception visible with its own nominated return owner. The distinct-owner fixture moves Q-IS to R-P4: the requirement names EX-SUBMITTER, the exception names EX-EXCEPTION-OWNER with offered disposition EX-DISP-47, and G1 names EX-GATE-OWNER with offered decision EX-GATE-91. The returned files preserve those differences; even the recorded-disposition claim leaves the requirement and gate PENDING. Thus two offered factory references do not become two covered site interfaces.

UNKNOWN identifies invalid records or a requirement without matching evidence metadata. PENDING means human review or a gate decision remains owed. Even matching evidence and nonempty decision references establish no authenticity, technical validity or authority. The checker cannot discover an omitted item or evidence slot when the declared inputs do not name it; it does not establish that an item’s requirement set is complete.

DOE’s federal-building guide supports keeping procedure review, factory-test review, witnessed results and deficiencies distinct. The record design and checks here are original examples. Use the linked physical-handoff guide for EX-HF51 and EX-H12 package-population examples, the punch-list guide for corrective-item closure, and the physical-layer verification service and project inquiry to discuss the actual physical deliverables.

References: [D1][L5]

  • Run the unchanged example first using the README instructions. Compare all four generated files with expected/baseline before editing an input.
  • Declare the required items and configuration revisions, then populate each required evidence slot and gate dependency. The checker checks fields, unique IDs, declared-item coverage, cross-references and dependency cycles.
  • Read report.json first. Invalid input suppresses item and gate conclusions; valid input can still contain UNKNOWN requirements. Exit 0 means the input could be checked, never that a gate was accepted.
  • Use the adverse fixtures to reproduce missing configuration, duplicate IDs, wrong revision or item, and unresolved exceptions. A declared decision must still leave its gate PENDING.
  • Read the separately labeled requirement, exception and gate return fields before routing each gap to its applicable nominated owner. Preserve the original CSVs: JSON retains the submitted form of included identifiers, while CSV viewing exports add an apostrophe before formula-leading values as the README explains.

Common planning questions

Can a physical ATP approve rack energization?

Not by itself. Energization belongs to the applicable facility/OEM and authorized electrical procedures and release decisions.

Is an as-built package the same as an ATP?

No. As-built records describe the installed configuration. The ATP defines verification and acceptance; its completed evidence can form part of the handoff package.

Does a missed witness automatically release a commissioning hold point?

Do not infer that release. The actual plan defines required attendance, notice, any permitted substitution or deferral, and who can authorize the next activity. An invitation, nonattendance or acknowledgement of receipt does not by itself record a different required technical or acceptance decision.

Does factory acceptance complete modular-data-center site acceptance?

Only the actual agreed scope can establish what each acceptance covers. Keep a matching factory report as evidence for its tested unit and configuration, then identify the site interfaces, conditions, changes and open items it does not establish. The appointed technical and accepting parties decide the required additional site evidence; the factory-tested description alone is not site acceptance.

Primary sources

  1. [F1] Fluke Networks: OLTS and OTDR testing strategyChecked 2026-10-14. Explains different measurement roles; not a project test method, limit or proof of Leviathan equipment.
  2. [L5] Leviathan physical-layer verification scopeChecked 2026-10-14. Formal procedures depend on confirmed personnel, instruments, method and acceptance criteria.
  3. [U1] UFGS 23 08 00: Commissioning of Mechanical and Plumbing SystemsChecked 2026-10-19. May 2023 guide specification, Change 1 August 2024; Certificate of Readiness section 1.6 and test scheduling section 3.8.1 read only as a named federal mechanical/plumbing example of prerequisites, signatures, approval and witnessing. No requirement, technical method, role assignment or permission is adopted for a GPU project.
  4. [D1] U.S. Department of Energy: Commissioning for Federal FacilitiesChecked 2026-10-19. Commissioning Process, printed pages 84–85, narrowly supports the distinction between procedure preparation/review, factory-test review, further required testing, witnessed functional testing and deficiency resolution. Historical federal-building guidance, not a GPU test method, current contract rule or proof of company commissioning capability.
  5. [S1] Schneider Electric: Prefabricated Data Center ModulesChecked 2026-10-19. Only the manufacturer's named factory-tested/partially assembled modular IT pod and factory-built data-hall modules joined on site descriptions are used to explain evidence boundaries. No capacity, timing, cost, performance, availability, project applicability or FAT/SAT completion claim is adopted.
  6. [NS1] NIST/SEMATECH e-Handbook, 6.2.1: What is Acceptance Sampling?Checked 2026-10-25. Explains the lot-disposition purpose of attributes acceptance sampling and distinguishes it from estimating lot quality. No GPU inspection requirement, sample size or release authority is adopted.
  7. [NS2] NIST/SEMATECH e-Handbook, 6.2.2: What kinds of Lot Acceptance Sampling Plans are there?Checked 2026-10-25. Explains a single-sample (n, c) plan and the operating-characteristic concept. No AQL, LTPD or producer/consumer-risk target is selected for EX-LOT-20.
  8. [NS3] NIST/SEMATECH e-Handbook, 6.2.2.2: Choosing a Sampling Plan with a given OC CurveChecked 2026-10-25. The binomial acceptance-probability treatment assumes a lot very large relative to the sample. EX-LOT-20 instead counts equally likely finite subsets exactly; the handbook does not prescribe its sample sizes or zero-finding rule.

Define the physical verification deliverables

Share the scope, equipment or links, proposed acceptance criteria and required report format so we can discuss what can be confirmed.

Discuss a ProjectEmail Project Scope