Field Guide · NVIDIA Rubin
NVIDIA Rubin: Define the Physical Work Package
A Rubin installation plan starts with the exact rack, its approved interfaces and the work each team is authorized to perform. A platform announcement cannot specify the cables to order, release a floor location or authorize a cooling connection. This guide turns the system documents into a reviewable physical work package.
The examples below use published NVIDIA DGX Vera Rubin NVL72 documentation. They do not establish compatibility with every partner-built Rubin system. Confirm the purchased SKU and current OEM documents before using a value. This is planning guidance, not a substitute installation procedure.
01Specifications
Four Specifications That Need an Exact System Context
Rack identity
NVIDIA documents DGX Vera Rubin NVL72 with 72 Rubin GPUs and 36 Vera CPUs, arranged in 18 compute trays, plus 9 NVLink switch trays. Source
Name the manufacturer, rack SKU, configuration and document revision on the work package. A Rubin-family label alone does not identify the equipment being received.
Power interface
The DGX hardware guide describes 415–480 V AC inputs to power shelves and an internal 54 V DC bus. That is a concrete counterexample to treating 800 V DC as mandatory for all Rubin installations. Source
The qualified electrical team must resolve the actual system input, capacity, protection and connection requirements. Power-shelf ratings are not a substitute for the approved rack load and facility design.
Cooling interface
The same DGX guide describes liquid-cooled compute trays and air-cooled power supplies. A liquid-cooled compute architecture does not establish that a room has no remaining air-cooling requirement. Source
Obtain the OEM thermal requirements and the facility team's accepted interface. Keep liquid-side installation, connection and testing outside the physical cabling work package.
External fabric
NVIDIA's DGX product specification lists 144 single-port OSFP ConnectX-9 interfaces at 800 Gb/s. A per-GPU aggregate bandwidth headline does not mean every external connector is a 1.6 Tb/s port. Source
Use the actual adapter, switch, optic and cable part numbers to build the port schedule. Confirm the protocol and link configuration instead of selecting cable by a platform headline.
Keep roadmap architectures and shipping system documents in separate columns of the project record. NVIDIA's 800 VDC discussion provides architectural context; it cannot supply this rack's approved voltage, breaker settings, cooling flow or handling method.
02Networks
Keep the Networks Distinct
The DGX guide separates the internal NVLink fabric from compute, storage and management networks. Rear tray connectors meet the NVLink cable-cartridge backplane; external port schedules describe a different set of interfaces. The documented DGX networking configuration assigns InfiniBand to its compute fabric and Ethernet to storage and management. Other configurations require their own approved network design. NVIDIA networking reference.
For the external physical package, record network purpose, rack and device IDs, exact port labels, cable and transceiver part numbers, and both endpoints. Keep the approved drawing revision beside the installed record. If a device label or port assignment differs from the released map, record the discrepancy for the network owner before treating the link as complete.
A label match is not proof that the fabric is configured, and a software bandwidth result is not a substitute for an as-installed cable record. Use a cable schedule alongside the materials list, then hand the agreed physical evidence to the network acceptance owner.
03Document sets
Request These Five Document Sets
A useful readiness review ends with named decisions. Mark each item accepted for the defined task, awaiting information or outside the package. Avoid a single “Rubin-ready” checkmark that hides an unresolved electrical interface or an unapproved cable revision.
| Document set | Required input | Responsible source and decision |
|---|---|---|
| Equipment and revision | OEM rack and tray identifiers; configuration/BOM revision; current installation and safety documents; shipment configuration. | Customer and supplying OEMCan the proposed scope be tied to one actual system? |
| Placement and handling | Approved rack location; equipment dimensions and loaded/shipping weights; delivery path; floor, lift and access constraints; authorized handling method. | Customer, facility and qualified handling specialistsIs the specific movement and placement permitted with the available resources? |
| Power and cooling readiness | The exact system interface documents and a readiness disposition from each responsible electrical/mechanical team, including unresolved conditions. | Customer-appointed OEM/facility specialistsWhich physical tasks may proceed, and which must wait for a specialist's release? |
| External cabling | Approved endpoint schedule; protocol and port mode; switch/adapter/optic/cable part numbers; pathway and label revisions; permitted system state. | Customer network lead and facilityCan every scoped cable be installed and identified without guessing an endpoint or substituting a part? |
| Checks and handoff | Agreed physical checks; evidence format; acceptance owner; exception process; separately confirmed formal-test resources if requested. | Customer acceptance owner and installation teamWhat demonstrates completion of the physical package, and what remains with another team? |
04Example
Example: One Conflicting Port Assignment
Illustrative record, not a customer project: a released cable schedule assigns a management connection to one port, but the delivered system's current interface document identifies that port for a different purpose. The installer records the rack/device identifier, both document revisions and the exact mismatch. The network owner supplies a corrected assignment or explains the configuration before that affected connection proceeds.
The closeout record retains the original discrepancy, the authorized resolution and the final endpoint/label pair. Unaffected work may proceed only within the site's approved sequencing and permissions. No replacement optic, electrical adjustment or cooling work follows merely because it would help the schedule.
This is the difference between reporting “cabling complete” and giving the next team evidence it can inspect. See the field-change record and physical handoff package for the supporting document structure.
05Installation boundary
Define the Installation Boundary Before Mobilization
Leviathan is ready to deploy Vera Rubin NVL72: equipment receiving and rack assembly, physical equipment mounting, structured cabling, routing, dressing, labeling, inspection, remediation and agreed physical verification and documentation. Customer-furnished equipment remains a valid project model. Physical relocation and lifecycle work require a defined inventory, custody responsibilities, destination and authorized tasks. Equipment placement, handling and lifts are reviewed against the actual site, safety conditions, resources and authorized scope.
Liquid-side and CDU work, facility electrical installation and cluster software commissioning stay with the specialists the customer appoints; the project documents their interfaces.
Agree the physical check and evidence needed for each deliverable. For hardware burn-in and QA, define the actual equipment, applicable OEM or customer method, conditions and duration, tools and personnel, recorded results, exceptions, retest decisions and acceptance criteria. A hardware result does not establish fabric or workload acceptance. OTDR, OLTS, copper certification or another formal method requires confirmation of the actual instruments, personnel, method and acceptance criteria. A general request to “test the rack” does not define any of those requirements.

06FAQ
NVIDIA Rubin FAQ
Is the standard Vera Rubin rack called NVL144 or NVL72?
Does every Rubin installation require an 800 V DC facility?
Can we order all Rubin fabric cables from a 1.6 Tb/s headline?
Does physical handoff establish that the GPU cluster is ready for workloads?
What can Leviathan scope for a Rubin project?
07Sources
Primary Sources and Applicability
Sources checked October 16, 2026. The cited DGX hardware and networking manuals identify their update as October 7, 2026. Retain the applicable revision with the project record and recheck it when the configuration changes. Source-backed product facts do not certify a site, a work method or an installer.
- 01NVIDIA DGX Vera Rubin NVL72 User Guide — HardwareRack composition, internal backplane, liquid-cooled compute trays and the documented AC-input power shelves.
- 02NVIDIA DGX Vera Rubin NVL72 specificationsThe named DGX system and its published external network-port specification.
- 03NVIDIA DGX Vera Rubin NVL72 User Guide — NetworkingDistinct scale-up, compute, storage and management interfaces; applies to the documented DGX configuration.
- 04NVIDIA 800 VDC architecture technical articleArchitecture roadmap context; not a universal electrical requirement for every Rubin rack.
- 05NVIDIA DGX Vera Rubin NVL72 User Guide — SafetyOEM safety information to accompany the exact system documentation and site-approved work method.
Contact
Discuss a Rubin Physical Work Package
Share the OEM configuration, site constraints, approved cable map and intended handoff. Our team will follow up to discuss scope, requirements and availability.