GPU cluster planning needs to distinguish the network’s logical roles from the physical equipment and paths that carry them. This topic collects references and buyer questions about compute, storage and management interconnects. A platform name or a pair of connections does not establish a topology, independent failure domains or accepted system performance.

Braided-sleeve cable bundles, strapped with hook-and-loop ties, sweeping in a matched radius toward switch ports.
Braided bundles, strapped and dressed to the port.

01Scope

Leviathan Systems Scope

Leviathan installs and documents customer-specified physical interconnects and management cabling. The customer or appointed network specialist owns topology, switch configuration, throughput testing and system acceptance.

02Failure domain

A different storage host is not necessarily a different physical failure domain

A failure-domain question asks which equipment or service can be affected together by a specified dependency. The useful physical question is therefore not simply whether storage nodes have different names. Ask which chassis, rack, power source and network components they rely on, and which failure the storage design is intended to address.

Ceph's versioned Squid documentation provides a concrete conceptual example. Its CRUSH map represents devices within a hierarchy such as hosts, chassis, racks and other physical groupings. The documentation identifies shared power and networking among the factors relevant to correlated failures. A hierarchy and its placement policy are separate: the representation of physical organization must be reconciled with the actual policy. This is a public storage-platform example, not a recommendation to deploy Ceph or change a running cluster. See the narrowly used primary source.

For physical rack planning, keep three objects distinct. The equipment population identifies the actual hosts, enclosures and their intended positions. The dependency description identifies relevant common equipment and boundaries. The storage policy identifies the responsible owner's actual distribution or availability requirement. Putting two hosts into two labeled racks does not, by itself, establish independent power or network paths, or confirm that the platform's modeled locations match the installed ones.

Ask the storage, network and facility owners which specific failure boundary matters and what evidence establishes it. The answer may require correcting an equipment-to-location record, obtaining an actual upstream dependency disposition, or revising a proposed arrangement through its design owner. Those returns are different from changing storage replication, moving data or relocating equipment. This topic provides no software commands, replica count, storage policy, power work, cable route, separation distance or approved placement.

03Rack change

Compare the dependency that a proposed rack change actually removes

EX-FD137 is fictional. It compares two proposed physical populations for the same two storage hosts, H1 and H2. In proposal A, both hosts are in chassis C1 and rack R1. In proposal B, H1 is in chassis C1 in rack R1, while H2 is in chassis C2 in rack R2. The stipulated dependency sheet still lists the same power-source reference P1 for both proposals, and supplies no complete network-path dependency. These are declared example inputs, not an actual equipment or facility design.

Proposal B changes the recorded chassis and rack grouping: two hosts are now assigned to two chassis and two racks instead of one of each. It does not remove the stipulated common P1 dependency. Nor does the absence of a network-path return prove that the paths are common or independent. A different rack identifier answers a location question, not every failure-domain question. The example makes no statement about data copies, usable capacity, service survival or an actual failure.

EX-FD137: proposed physical grouping and remaining dependency are different conclusions
Example boundaryProposal AProposal B and unresolved meaning
Host populationH1 and H2: two hosts.The same two hosts; no added storage capacity or data-protection result is stipulated.
Chassis and rack groupingOne chassis C1 in one rack R1.Two chassis C1/C2 in two racks R1/R2. The recorded physical grouping differs; actual placement suitability remains unassessed.
Power-source referenceP1 is common to the two hosts in the example.P1 remains common. Changing the rack labels has not changed that stipulated dependency.
Network dependencyComplete path information is not returned.Still unknown. Two ports, cable labels or rack positions do not establish the missing path relationship.

Before a physical work package relies on proposal B, the appointed owners must decide whether its actual dependencies satisfy the intended requirement, identify the applicable released arrangement and state any unresolved scope. Keep that decision distinct from a later record of where equipment was installed. If the physical population or a shared dependency changes, return the affected arrangement and the storage model's applicability to their respective owners; do not silently update one diagram and declare the service resilient.

The physical handoff can link the equipment identities, positions, issued arrangement, returned dependency references, observed scope and open decisions. It cannot itself establish the storage configuration, failure behavior or continuity of an application. Use the handoff evidence guide for the distinct record package. No component is removed, disconnected, tested or approved by this example.

Ceph Squid documentation — CRUSH Maps, checked October 19, 2026. Only the conceptual distinction between physical hierarchy, correlated dependencies and placement policy is adopted. No commands, software configuration, data movement, replica count, security or availability guarantee, installation procedure or actual site approval is supplied.