title: "GPU Rack Receiving and Movement: Prepare the Review Package"
description: "Leviathan Systems — Technical content Published 2026-06-23; updated 2026-10-20."
canonical: "https://www.leviathansystems.co/articles/gpu-rack-receiving-rigging-lift-plan"
last-updated: "2026-10-20"
---

# GPU Rack Receiving and Movement: Prepare the Review Package

Leviathan Systems — Technical content
Published 2026-06-23; updated 2026-10-20.

Before a heavy GPU rack or server shipment arrives, identify the exact delivered assembly, its packaging and applicable OEM documents. Connect those records to the approved receiving point, staging area, movement route and named handling and facility owners. Keep delivery receipt, permission to move and installation acceptance separate. This guide prepares that evidence package; the qualified project parties must determine lifting methods, equipment, floor suitability and site-specific approvals.

## Identify the assembly and state being reviewed

Begin with the supplier's full system or rack model, ordered configuration and shipment reference. State whether the delivery consists of individual servers, a configured rack, separate accessories or multiple assemblies. Match the packing list to that description. A project title such as Blackwell deployment cannot supply the dimensions and handling restrictions for each item that arrives.

Then identify the state covered by each document: packaged for transport, at an approved unpacking point, in the approved movement arrangement, or installed at its destination. Keep packaging, shipping supports and included accessories visible in the record. Any change of state must be reviewed under the applicable OEM and site instructions; the article does not determine when packaging should be removed.

NVIDIA's DGX B200 overview provides mechanical specifications for the named system. Its DGX H100 planning guide separately labels product-weight, chargeable-weight, pallet-weight and product-box-dimension fields. Those examples show why a number headed weight is insufficient without its definition. Obtain the supplier's actual shipment data rather than transferring an H100 or B200 value to an NVL72 rack.

References: [N1](https://docs.nvidia.com/dgx/dgxb200-user-guide/introduction-to-dgxb200.html), [N3](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/planning.html)

Give every mechanical record a defined equipment state
| Record | What it describes | What to resolve | Source |
| --- | --- | --- | --- |
| System mechanical specification | The exact configured server or rack identified by the document | Whether the delivered options and assembly match this specification | Planning analysis |
| Shipment and packaging record | The actual crate, pallet or other shipped package | Dimensions, mass, package identifiers and OEM restrictions for that shipment | Planning analysis |
| Movement arrangement | The assembly and handling arrangement reviewed for a route segment | Which qualified party has assessed that arrangement and its applicable instructions | Planning analysis |
| Installed destination record | The released final location and equipment configuration | Which facility and installation approvals apply after movement | Planning analysis |
This is an original document-classification aid. It provides no weight allowance, load calculation, packaging-removal sequence or handling technique.

## Confirm the receiving boundary with the operator

Ask the site operator what it will receive, the arrival window, the permitted delivery point and who owns the handoff from the carrier. Confirm any required shipment reference, access order, staging arrangement and later transfer to the customer space. Put the actual operator decision in the package so the field team can retrieve it.

Equinix provides a specific example: its published inbound process requests shipment size, weight, package counts and special handling instructions for oversized items. It also assigns movement between the delivery vehicle and loading dock to the carrier rather than IBX personnel. These are Equinix process boundaries, not universal rules for other operators or proof that an unusually heavy shipment has been accepted. Confirm the applicable facility arrangement directly.

The separate receiving-and-staging guide covers the custody record and shipment-condition observations. Here, retain its reference and concentrate on the next boundary: who may release the identified equipment from the receiving area into the approved movement package.

References: [O1](https://docs.equinix.com/smart-hands/shipping-receiving/sh-inbound-shipments/)

## Prepare a route evidence worksheet for qualified review

A route drawn from loading dock to rack position needs a supporting record for the actual equipment state at each stage. Ask the responsible site and handling parties to identify the assessed route, its revision, any required movement window and the points where responsibility or equipment state changes. Record references to their assessment rather than replacing it with a generic clearance number.

NVIDIA's H100 data-center infrastructure guide distinguishes support for the installed racks from support for ingress and egress pathways carrying equipment and its conveyances. That is a useful review boundary, not a floor-capacity result for this project. The qualified facility party must determine what the actual route and supporting structures can accept. A floor tile label or an average rack-weight figure cannot, by itself, close that question.

Use the following original worksheet to expose missing decisions. Each line should point to evidence or a named unresolved item. Keep detailed site drawings and access-sensitive information in the project's controlled records.

References: [N4](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html)

GPU equipment movement-readiness evidence worksheet
| Review item | Evidence or reference to retain | Decision owner to identify | Source |
| --- | --- | --- | --- |
| Shipment identity and state | Actual assembly, package identifiers, supplier data and applicable OEM document revisions | Customer equipment owner and supplier | Planning analysis |
| Vehicle-to-receiving handoff | Approved receiving point, arrival arrangement and carrier/operator responsibility boundary | Carrier and facility receiving authority | Planning analysis |
| Staging or unpacking location | Permitted location, applicable packaging instructions and released scope for the activity | Site operator and OEM/authorized handling owner | Planning analysis |
| Movement route and transitions | Assessed route revision, equipment state by segment, access constraints and relevant facility records | Qualified handling lead and site/facility authority | Planning analysis |
| Structural and vertical-transport review | Disposition for the actual equipment/conveyance arrangement and affected floor, elevator or other interfaces | Appropriately qualified facility/structural authority | Planning analysis |
| Method and execution readiness | Reference to the project-specific handling plan, authorized personnel and applicable equipment documentation | Qualified handling contractor and required site approvers | Planning analysis |
| Destination handoff | Released location, receiving party and outstanding restrictions before physical installation | Customer installation owner and site authority | Planning analysis |
The worksheet identifies inputs and owners. It is not a lift plan, structural approval, equipment-selection rule or authorization to begin movement.

## Name the handling and technical authorities

Record who develops and authorizes the actual movement method, who accepts the site route and structural questions, and who controls OEM installation or service work. One party may hold several roles, but the package needs evidence of each applicable responsibility. A general installation engagement does not establish every party's authority to lift equipment, approve floor loading or service the system.

Product requirements matter here. NVIDIA's DGX B200 guide requires installation by NVIDIA partner network personnel or NVIDIA field service engineers, and requests that site information be supplied to the installation partner. The DGX GB safety guidance also reserves integration and service for technically qualified persons. These statements concern the cited products.

Ask the supplier to resolve the boundary between the handling contractor, OEM installation party and agreed physical installer for the purchased system. Retain their instructions and the applicable project scope. Actual methods, personnel, equipment suitability and site approvals remain with the qualified parties responsible for those decisions.

References: [N2](https://docs.nvidia.com/dgx/dgxb200-user-guide/quickstart-basics.html), [N5](https://docs.nvidia.com/dgx/dgxgb200-user-guide/safety.html)

## Separate receipt, movement and system acceptance

Describe what each completion record proves. A receiving record can establish the shipment reference, observed package condition, count and custody at a stated location. A movement handoff can establish the agreed transfer and any recorded exceptions. Neither automatically establishes concealed condition, completed installation or system function. Agree the evidence and accepting party for each boundary before treating a status as complete.

Damage handling also follows the actual operator, carrier and supplier process. For example, Equinix's published policy says visibly damaged shipments are accepted and photographed, with notification to the shipping contact. A universal instruction to reject every visibly damaged package would misstate that example. Refer discrepancies to the authorized owner using the agreed process; this article does not decide commercial acceptance, warranty coverage or a claim deadline.

Keep system inspection, electrical or liquid-side work, diagnostics and workload acceptance in their separately authorized packages. The receiving or movement team should report the observed condition and documented handoff rather than adding a commissioning-complete statement to close a logistics ticket.

References: [O1](https://docs.equinix.com/smart-hands/shipping-receiving/sh-inbound-shipments/)

## Reconcile a changed shipment against the reviewed route

Illustrative example: the receiving package refers to crate R2, but the supplier issues revised packaging dimensions after the route review. Keep the earlier record and the new supplier revision linked to the same shipment. Identify which route assessment used the earlier dimensions, then ask its responsible reviewer to resolve whether the existing decision still applies. Record that disposition before relying on the old release.

The same document check is useful when the destination, delivery state or proposed movement arrangement changes. A revised final rack position may change which route or facility records are relevant. A checked box should name the configuration and revision it covers. It cannot serve as an indefinite approval for any later assembly sent under the same project name.

Report a concise open item: affected assembly, changed input, governing reference, decision owner and required disposition. That gives the coordinator a useful question to resolve without asking the field team to invent a substitute handling method.

## Connect the Blackwell architecture to the actual shipment

A Blackwell rack question starts by identifying the delivered object. NVIDIA's DGX GB hardware guide describes a rack-scale system containing compute trays, NVLink switch trays, a passive copper cable backplane, power shelves, a bus bar and liquid cooling manifolds. Its compute-tray description concerns one enclosure within that system. Neither the GPU name nor the tray description identifies the complete packaged shipment.

Use that distinction to ask the supplier a precise question: does the order line identify a complete configured rack, a separately shipped tray or server, or an accessory package? Link each delivered package identifier to the ordered assembly and its configuration. If the supplied dimensions describe an installed rack while the arrival record describes a crate, keep both records with their stated meanings. Do not silently relabel one as the other.

The comparison below is an original document crosswalk, not a specification of how any manufacturer ships equipment. The purchased configuration, package dimensions and mass must come from the actual supplier records. A public architecture page cannot confirm included accessories, shipping supports, packaging or movement state for an order.

A useful Blackwell receiving question therefore names the missing field: which package and configuration does this dimension or mass describe, which document revision provides it, and which route review used that same state? Until those references agree, an attractive rack elevation or a GPU count is insufficient evidence for the receiving and handling decision.

References: [N6](https://docs.nvidia.com/dgx/dgxgb200-user-guide/hardware.html)

Distinguish the named product from the delivered object
| Reference in the request | What the reference can identify | Shipment question still to resolve | Source |
| --- | --- | --- | --- |
| Blackwell or a GPU count | A component family or population description | Which complete system, configuration and packages are being delivered? | Planning analysis |
| DGX GB rack hardware description | The named rack-scale architecture and its component classes | Does the actual order and packing list describe that complete rack and the stated delivery state? | Planning analysis |
| Compute-tray or individual-server document | The identified component or server at the state specified by its document | Is that item shipped separately, installed in the delivered rack, or merely referenced in the equipment list? | Planning analysis |
| Supplier shipment and package record | The identified package and its declared contents, dimensions and mass | Which OEM instructions and qualified route/handling decision apply to that package and subsequent movement state? | Planning analysis |
Original buyer crosswalk. It supplies no crate size, mass, packing arrangement, handling method or permission to change the delivery state.

## Retain loading positions as well as total mass

A rack-loading document should preserve which equipment and accessories the reviewed arrangement contains, not just a total labeled rack weight. Keep the cabinet identity, equipment configuration, component-position drawing, applicable mounting references and the state covered by the mass data together. A position change can leave an inventory count unchanged while making the earlier arrangement record inaccurate.

The H100 infrastructure guide includes peripheral equipment and cabling in its rack-weight discussion, says exact loaded weight depends on the actual cabinet and contents, and distinguishes installed-equipment support from movement-path support including conveyances. Those are reasons to request the correct input set. They do not provide a floor rating, contact-load distribution or approved arrangement for a different rack.

Fictional register EX-LD100 contains three input records. A proposed equipment-position change is recorded in one; accessory mass is missing in another; the cabinet/support-interface record is still unresolved. P1 and P2 below are arbitrary position references in a drawing, not rack-unit locations or placement instructions. No mass, center of gravity or allowable load is calculated.

Give the responsible equipment and facility reviewers the revised arrangement and the unresolved data, with links to the earlier revision. Ask them to identify which prior dispositions remain applicable and which need an updated response. Document their response against the exact assembly and state; do not infer it from an unchanged item count or a total copied from another configuration.

References: [N4](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html)

EX-LD100: three fictional loading-document inputs with different open decisions
| Input record | Current evidence | Change or missing information | Return needed from the responsible owner | Source |
| --- | --- | --- | --- | --- |
| EX-S1 equipment entry | Configuration EQ1 and mass-document reference MD1 are linked to arrangement F1 at position P1 | Arrangement F2 proposes the same identified unit at P2 | Equipment/mounting owner disposition for F2 and the resulting qualified facility review reference; unchanged count does not approve F2 | Planning analysis |
| EX-A1 accessory entry | The cabinet list identifies an accessory in the arrangement | Its applicable mass/configuration reference is absent | Supplier/equipment owner supplies the missing reference or leaves the item explicitly unresolved; do not enter zero as an assumption | Planning analysis |
| EX-C1 cabinet and support-interface entry | The cabinet model is identified | Applicable loaded arrangement and support/contact-interface evidence have not been returned | Qualified cabinet/facility parties identify the applicable records and disposition; the register supplies no point-load or structural result | Planning analysis |
Three documentary input records, one proposed position change and two other unresolved inputs. No received measurements, approved placements, completed moves or engineering results are represented.

## Link a rack move to the frozen cable and route package

After a cable-length freeze, a destination change needs a named impact set rather than a note saying move the rack. Keep the equipment identity separate from its location: the rack can remain EX-R1 while the proposed location changes from R21 to R22. Identify the layout revision, affected connection IDs and released movement-route reference that used R21. A room label or a statement that the move is short does not resolve those dependencies.

NVIDIA's H100 design guide explains that cabinet geometry and overhead routing layout affect cable lengths. That is a configuration-specific reason to revisit the relevant cable design, not a distance allowance for the proposed move. The cabling designer must decide the applicable route, supported assemblies and lengths for the actual system.

Fictional change EX-MV101 concerns rack EX-R1 only. Layout LY4 and cable schedule CS7 are the earlier controlled references. A proposed LY5 changes EX-R1's location from R21 to R22. The two connection records below show why an item-level comparison is more useful than declaring all cables reusable or all cables replaceable. The example supplies no cable lengths or actual route geometry.

First, retain LY4, CS7 and the prior movement-release reference with the change request. Then return the proposed LY5 location and the identified connection differences to their responsible design, facility and movement owners. A revised cable response must identify its governing layout and route; a revised movement response must identify the assembly/state and destination it covers. Record the issued revisions, unresolved items and the installation package that will use them. A proposed drawing is not an issued change, and an updated cable schedule does not by itself release equipment movement.

If delivery must remain scheduled while those responses are pending, the coordinator should obtain the actual receiving and staging disposition for that circumstance. Do not replace the missing decisions with an improvised movement or patching sequence. This is a worked change-control example, not a direction to move EX-R1 or reuse any cable.

References: [N4](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html)

EX-MV101: compare two connection identities against one proposed rack-location change
| Connection identity | Earlier controlled record | Proposed difference | Decision and revision linkage | Source |
| --- | --- | --- | --- | --- |
| EX-C101 associated with EX-R1 | CS7 references EX-R1 at R21 under LY4 and its released route | LY5 proposes R22; no revised cable route or length has been returned | Cabling designer returns the applicable route/assembly/length disposition and issued schedule revision; keep the connection unresolved until that response is recorded | Planning analysis |
| EX-C102 associated with a different rack EX-R2 | CS7 references EX-R2 at R31 | No endpoint or location-field change is shown in LY5 for this record | Do not invent an endpoint change; still ask the route owner whether any shared pathway or other dependency is affected before excluding it from the impact set | Planning analysis |
Two fictional connection records: one identified endpoint-location dependency and one unchanged endpoint/location comparison requiring an impact-boundary check. Zero length calculations, reuse approvals, released moves or physical work.

## Verify the opening package without inventing an unpacking method

Before a factory-packaged rack is opened, the receiving package should make the intended action and its authority explicit. Opening an outer shipping enclosure, removing transport restraints, moving the rack and servicing an internal component are different activities. Do not assume that a delivery receipt or a general access order covers all of them. The applicable OEM, supplier, operator and authorized handling instructions determine the actual activity.

Use the questions below to expose a missing reference before anyone treats the paperwork as a release. They are an original document check, not an unpacking sequence. For the named DGX B200 product, the retained installation-party requirement still applies; the checklist does not appoint a contractor or extend a server instruction to a factory-packaged rack.

Record the response at the same level as the question. For example, a package label matching the order can close that identity comparison while the authorized opening party or location is still unresolved. A photograph or a status reading received should not be used to change the unresolved opening decision to approved. If a supplied document and the package identify different assemblies or revisions, return that specific discrepancy to the supplier and responsible handling/site owners. Do not fill the gap with instructions for another model.

Keep the original shipment-condition observations, the applicable discrepancy response and the later opening/movement records linked. This preserves what was known before the condition changed. It does not determine concealed condition, warranty, damage responsibility, claim deadlines or system acceptance.

References: [N2](https://docs.nvidia.com/dgx/dgxb200-user-guide/quickstart-basics.html), [N5](https://docs.nvidia.com/dgx/dgxgb200-user-guide/safety.html)

- Identity: do the package identifiers, order/configuration and actual packing-list references describe the same delivered assembly?
- Document and state: which applicable OEM/supplier revision addresses this packaging and the precise activity now proposed?
- Place and responsibility: what location and scope did the operator release, and who is the authorized handling or OEM party for this action?
- Condition record: what permitted external observations and discrepancies were recorded before opening, and where is the applicable supplier/operator response?
- Dependencies: which movement, storage or installation decisions depend on keeping or changing this packaging state, and are their responsible-owner responses available?
- Return record: who records the changed state, resulting handoff and remaining exceptions, without treating receipt or opening as system acceptance?

## Match the handling tool to the unit and task

A handling resource is described by its task and interface, not just by a lifting-capacity number. The distinction is concrete in NVIDIA's DGX H100 infrastructure guide: its server-lift discussion describes a platform that supports the sensitive chassis and distinguishes that arrangement from a general materials lift using forks. A tool described as capable of lifting the weight is therefore not automatically the type described for that server task. This is a named H100 reference, not a rule selecting a tool for every GPU server or a direction to lift one. [N7]

Keep the three work boundaries separate. Delivery equipment serves the identified shipped load at the carrier or receiving boundary. A server-handling arrangement serves the particular chassis and its transition to or from a cabinet. Installation responsibility identifies who is authorized for the purchased product. NVIDIA's H100/H200 quickstart separately assigns installation to NVIDIA partner network personnel or NVIDIA field service engineers and asks that site information reach the installation partner. An available vehicle or lift does not establish that personnel status, and an installation-party name does not establish that the right handling equipment is present. [N8]

For the buyer, resolve those different assertions before treating a return such as team and lift booked as readiness evidence. Identify the delivered object and intended task; ask the responsible handling party to confirm the applicable equipment type, interface and manufacturer requirements, and the actual personnel and site arrangements. Keep this confirmation distinct from the supplier's installation-party requirement. This article sets no staffing count, load rating, lifting height, attachment point, maneuver, unpacking sequence or work permission.

Fictional EX-HT152 compares two proposed equipment descriptions for the same stipulated bare DGX H100 chassis task. These are two proposal lines, not two tools present at a site. One describes a forked general materials lift; the other describes a platform server lift. Against the cited H100 description, the first has an equipment-class conflict and the second has one class-level agreement. Neither line supplies the actual equipment specification, task-specific applicability, personnel or assessed site conditions. There are two compared lines, one conflict, one limited agreement and zero ready handling packages.

Return the specific conflict rather than solving it with an extra person or a remembered lifting limit. The appointed handling and installation parties must resolve the actual arrangement under the applicable documents. The existing route worksheet still applies to the equipment and conveyance together; it cannot be closed by confirming the chassis identity alone.

References: [N7](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html#server-lifts), [N8](https://docs.nvidia.com/dgx/dgxh100-user-guide/quickstart-basics.html)

EX-HT152: equipment class is one readiness comparison, not a handling release
| Fictional proposed description | Comparison with the named H100 reference | What that comparison leaves unresolved | Source |
| --- | --- | --- | --- |
| HT-A: forked general materials lift proposed for the bare chassis task | Conflicts with the cited distinction between a platform server lift and forked materials equipment for this named task. | The responsible owner must resolve the equipment description and applicable arrangement. No substitute tool, staffing or method is selected. | N7 |
| HT-B: platform server lift proposed for the same bare chassis task | Matches the described equipment class only; this is not evidence that an actual model or configuration is suitable. | Actual model and task applicability, equipment condition, authorized personnel, site and route assessment, and required release remain absent. | N7 |
Entirely fictional two-line comparison. One equipment-class conflict, one class-level agreement and no physical equipment, completed lift, approved route or safe-work result. No tool is recommended.

## Prepare the physical installation handoff

Once the qualified receiving and movement decisions are recorded, the next team needs the identified equipment, released destination, applicable OEM instructions and any remaining restrictions. Link the custody record and route-review reference to the installation work package. Use the existing site-readiness guide for rack, cable and facility-interface dependencies, and the as-built guide for the agreed installation evidence.

For a Leviathan discussion, share the complete system model, equipment quantities, customer site, proposed timing and approved documents relevant to the physical work. Leviathan delivers rack-and-stack and cabling, and scopes equipment receiving and delivery coordination; identify the appointed supplier and delivery responsibilities. Rack placement, equipment handling and lifting requirements are reviewed for the particular engagement.

References: [L1](https://www.leviathansystems.co/services/rack-and-stack)

## Common planning questions

### Can the GPU model determine the rack shipment's weight and movement requirements?

No. Obtain the exact assembly and shipment records, including the packaging and configuration they describe. A GPU family or a mechanical specification for an individual server does not define the delivered rack, its transport state or the site-specific movement method.

### What should facility engineering receive for a movement-route review?

Provide the actual assembly and packaging data, proposed equipment state and movement arrangement, route references, destination and applicable OEM documents. The responsible qualified party must determine the required structural and facility assessment. This article provides no floor-load calculation or approval.

### Is this worksheet a rigging or lift plan?

No. It identifies documentary inputs, unresolved questions and decision owners. The qualified handling party and required site approvers must develop and authorize the actual method, personnel and equipment for the project.

### Does the facility receiving a crate mean it is ready for installation?

Receipt, movement release, installation and system acceptance are separate decisions. Record which one has been completed, by whom, for which configuration and with what exceptions. Use the applicable operator, supplier and customer process for damage or discrepancies.

### Does the DGX GB rack hardware description establish its shipping dimensions and mass?

No. It describes the named rack-scale architecture and its components. The actual supplier shipment records must identify the ordered configuration, package, contents and state covered by the dimensions and mass. Do not substitute a compute-tray or installed-rack reference for the delivered package.

### Can an unchanged equipment count make an earlier rack-loading review applicable after a position change?

Not by itself. Retain the equipment identities, configuration/mass references and revised position drawing, then obtain the responsible equipment and qualified facility dispositions for that arrangement and state. An inventory total is not a distribution, support-interface or structural approval.

### What should change control return when a rack moves after cable lengths were frozen?

Link the exact rack/location and layout change to the affected connection IDs, cable route/assembly/length disposition, movement-route review and issued installation references. Preserve earlier revisions and identify unresolved decisions. A proposed location or a revised cable list alone does not approve cable reuse or release the rack move.

### Does an adequate advertised lift capacity establish the right equipment and team for a GPU server?

Capacity is one field. Match the actual task, equipment type and supporting interface to the applicable product and handling requirements. The named H100 guide distinguishes platform server lifts from forked materials equipment, while H100/H200 installation-party requirements are a separate issue. The actual qualified parties must establish equipment suitability, personnel and site readiness; the comparison supplies no staffing ratio, universal rating or handling permission.

## Primary sources

- [N1 — NVIDIA DGX B200 User Guide: mechanical specifications](https://docs.nvidia.com/dgx/dgxb200-user-guide/introduction-to-dgxb200.html). Checked 2026-10-15. Uses the named system's mechanical-specification boundary only; no shipment mass, crate dimensions or rack-scale handling values inferred.
- [N2 — NVIDIA DGX B200 User Guide: installation and configuration](https://docs.nvidia.com/dgx/dgxb200-user-guide/quickstart-basics.html). Checked 2026-10-15. Uses the explicit DGX B200 installation-party and site-information requirements. No start-up, test or operating procedure adopted.
- [N3 — NVIDIA DGX H100 data-center design guide: planning and safe system delivery](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/planning.html). Checked 2026-10-15. Uses the separately labeled product/pallet/box fields as a documentary example. H100-specific figures and procedures are not transferred to B200, NVL72 or any actual shipment.
- [N4 — NVIDIA DGX H100 data-center design guide: white-space infrastructure](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html). Checked 2026-10-15. Uses the distinction between installed-equipment support and equipment-plus-conveyance movement-path assessment. No sample rack weights, floor loads, lift ratings, mounting or anchoring methods adopted.
- [N5 — NVIDIA DGX GB Rack Scale Systems User Guide: safety information](https://docs.nvidia.com/dgx/dgxgb200-user-guide/safety.html). Checked 2026-10-15. Uses the technically qualified integration/service-party boundary only. No generic electrical, handling, anchoring or liquid procedure adopted.
- [O1 — Equinix IBX inbound shipment documentation](https://docs.equinix.com/smart-hands/shipping-receiving/sh-inbound-shipments/). Checked 2026-10-15. Specific operator examples for shipment data, carrier-to-dock responsibility and visible-damage records. Actual site arrangements and shipment acceptance require operator confirmation; no contract interpretation or universal schedule/retention rule.
- [L1 — Leviathan Systems rack-and-stack service scope](https://www.leviathansystems.co/services/rack-and-stack). Checked 2026-10-15. Current public physical service scope.
- [N6 — NVIDIA DGX GB Rack Scale Systems User Guide: hardware and rack configuration](https://docs.nvidia.com/dgx/dgxgb200-user-guide/hardware.html). Checked 2026-10-19. Named rack-scale component classes and compute-tray versus complete-rack documentary boundary only. No package dimensions, mass, shipping state, included order contents, rack suitability or handling procedure inferred.
- [N7 — NVIDIA DGX H100 data-center design guide: named server-lift equipment distinction](https://docs.nvidia.com/dgx-superpod/design-guides/dgx-superpod-data-center-design-h100/latest/infrastructure.html#server-lifts). Checked 2026-10-19. Named H100 platform server-lift versus forked general materials-lift distinction only, from Server Lifts. No numerical capacity, mounting position, clearance, handling step, universal equipment rule, site suitability or work permission transferred. The earlier N4 object remains unchanged for its separate source scope.
- [N8 — NVIDIA DGX H100/H200 quickstart: installation-party and site-information boundary](https://docs.nvidia.com/dgx/dgxh100-user-guide/quickstart-basics.html). Checked 2026-10-19. Installation and Configuration paragraphs only: named installation-party and site-information requirements. No warranty interpretation, eligibility assertion for any company, registration, operating, diagnostic, software or service procedure adopted.

## Related Leviathan resources

- [Receiving and staging GPU equipment: maintain the custody record](/articles/receiving-staging-gpu-equipment)
- [GPU site readiness: review the wider installation inputs](/articles/site-readiness-before-gpus-arrive)
- [Colocation access: reconcile the permitted people, place and task](/articles/colocation-installation-work-authorization)
- [GPU installation RFP and SOW: define the physical work package](/articles/rfp-sow-checklist-gpu-build)
- [GPU installation handoff: retain records, revisions and open items](/articles/as-built-handoff-package-gpu-deployment)

## Discuss the physical installation handoff

Share the equipment model, site requirements and available approved documents. Our team will follow up to discuss the physical scope, requirements and availability.

[Discuss the scope](/contact?service=rack-and-stack&from=/articles/gpu-rack-receiving-rigging-lift-plan)